Townland of Ballysumaghan Fannybrook, Quarry Lane Co. Sligo, Ireland
Construction of a battery energy storage system compound on a 5.05 hectare site in Sligo.
2360214 · Sligo County Council · Lodged 17 August 2023
- Reference
- 2360214
- Authority
- Sligo County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 17 August 2023
Summary
AI-generatedThe 10-year planning permission application is for an enclosed battery storage compound containing 150 battery units. It includes a two-storey 220kV Gas Insulated Substation, a customer control building, backup generators, firewater reservoir ponds, and access road upgrades.
- Storeys
- 2
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- A 10 year planning permission for the construction of a
- Enclosed battery energy storage system compound on a total of up to c. 5.05 hectare site, to include
- 150 battery units set inside storage blocks on concrete support structures containing heating, ventilation and air conditioning unit (hvac units)
- Transformer and inverter units on concrete support structures
- 1 no. Two storey customer 220kv gas insulated substation (gis) (see drawing 23553-201 and 23552-202)
- 1no. Customer control building and 220kv transformer with associated switchgear
- 3no. Containing back-up generators, auxiliary transformers, switchgear containers, lv and control containers
- 1no. Lightning pole
- 2no. Firewater reservoir ponds with pumping station and 1no. Detention basin with associated drainage systems (as per drawing 23553-102)
- Security gates, 2.6m palisade perimeter security fencing, cctv and lighting system, landscaping works and all associated ancillary infrastructure
- 4.5m wide access tracks and site entrance along with upgrade works on the public site access road (c. 950m)
- Associated electrical cabling and ducting and all other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of areas of hard standing including a maintenance lay-down area
- C. 100m of underground cabling ducts and cable to the neighbouring esb substation. A natura impact statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts. The development will be located at a site in the townland of ballysumaghan, fannybrook, quarry lane co. Sligo. The proposed development will have a projected life span of 35 years
Key dates
Timeline
- Application received17 August 2023
- Decision due11 October 2023
- Decision issued10 October 2023
- Grant issued14 November 2023
- Permission expiry13 November 2028
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decision40 m away
Development consisting of the development of a battery energy storage system. The development will consist of…
Townland of Ballysumaghan , Fannybrook , Quarry Lane
22369SligoLodged 9 Nov 2022Energy
- Granted70 m away
Development consisting of a 10 year permission. The development will consist of the development and operation…
Ballysumaghan , Sooey , Co Sligo
2090SligoLodged 19 Mar 2020Energy
- Granted300 m away
The development will consist of amendments to the permitted but not yet constructed Synchronous Compensator…
Ballysumaghan , Sooey , Co. Sligo
2560170SligoLodged 2 May 2025Energy
- Granted400 m away
Development consisting of the erection of a 2.4m high palisade fence with pedestrian only access gate within…
Ballysumanagh , Srananagh , Co. Sligo
16405SligoLodged 19 Oct 2016Infrastructure
- Granted400 m away
Development consisting of (a) A High Inertia Synchronous Compensator (HISC) compound containing 1 No. HISC…
Ballysumaghan , Sooey , County Sligo
22352SligoLodged 27 Oct 2022Energy
- Granted400 m away
The development will consist of an enclosed battery energy storage system compound on c. 2.04 hectares. The…
Townland of Ballysumaghan , Srananagh , Co. Sligo
2560036SligoLodged 5 Feb 2025Energy
- Granted410 m away
Development consisting of the erection of a 36m high lattice communication structure carrying antennae,…
Ballysumaghan , Sranagh , Co. Sligo
2185SligoLodged 15 Mar 2021Infrastructure
- Granted480 m away
Development consisting of the installation of battery arrays, located within container units (18 number…
Ballysumaghan , Co Sligo
2011SligoLodged 21 Jan 2020Energy
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
Development consisting of the development of a battery energy storage system. The development will consist of…
Townland of Ballysumaghan , Fannybrook , Quarry Lane
22369SligoLodged 9 Nov 2022
- Awaiting decisionEnergy
Permission for — 1no. enclosed battery energy storage system compound on a total of c. 2-hectare site, to…
Ballynanelagh Knockraha Co. Cork
25/4155corkLodged 7 Feb 2025
- Awaiting decisionEnergy
Permission for 1 no. enclosed battery energy storage system compound on a total of c. 2 hectare site, to…
Ballynanelagh Knockraha Co Cork
24/6103corkLodged 6 Nov 2024
- GrantedEnergy
The development will consist of an enclosed battery energy storage system compound on c. 2.04 hectares. The…
Townland of Ballysumaghan , Srananagh , Co. Sligo
2560036SligoLodged 5 Feb 2025
- GrantedEnergy
For development which will consist of: 1 No. enclosed battery energy storage system compound on a total of c.…
Ballygeery West , Co. Clare
2360393ClareLodged 22 Sept 2023
- RefusedEnergy
A 10 year planning permission for the construction of — An enclosed battery energy storage system compound on…
Dunnstown , Co. Kildare.
21608KildareLodged 6 May 2021
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.