Planning Permission Ireland
GrantedEnergyDecided 11 November 2013

Hynestown, Newcastle, Co. Dublin.

Construction of a farm-based anaerobic digester plant to produce renewable energy and fertiliser.

SD13A/0093 · South Dublin County Council · Lodged 16 October 2013

Reference
SD13A/0093
Authority
South Dublin County Council
Register status
Decided
Type
Permission
Received
16 October 2013
Floor area
502 m²

Summary

AI-generated

Permission is sought for a farm-based anaerobic digester to process slurry and organic waste. The project includes converting an existing farm building, building an office, storage buildings, digester and storage tanks, a flare stack, a weighbridge, and connecting an ESB substation to the National Grid.

Energybioenergyagriculturerenewableinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Construction of a farm based anaerobic digester to process farm slurry and other organic material to produce renewable energy and fertiliser; change of use of existing farm building to anaerobic digester plant building; construction of a detached office building; construction of 2 no. Storage buildings; upgrade of the existing entrance; construction of a flare stack with height of 5.16m above proposed ground level (r. L = 76.36m above msl malin); installation of 2 no. Digester tanks with height of 12m above proposed ground level (r. L. Range = 82.83
  • 83.11m above msl malin); installation of 2 no. Storage tanks with height of 6.87m above proposed ground level (r. L. = 77.37m above msl malin); construction of a weighbridge; construction of an esb substation and connection to the national grid; installation of an effluent treatment unit and percolation area to cater for on site toilet facilities; construction of a landscaped berm around the facility; construction of a wheel wash facility; construction of 2 no. Stormwater attenuation tanks and all associated site works

Land-use zoning

What this land is zoned for

RURU
To protect and improve rural amenity and to provide for the development of agriculture

Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 4 January 2016.

3 commencement notices are linked to this development.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Peamount Rd, Hynestown, NewcastleApr 2025€1,250,000355 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received16 October 2013
  2. Further information requested4 July 2013
  3. Further information received16 October 2013
  4. Decision due12 November 2013
  5. Decision issued11 November 2013
  6. Grant issued19 December 2013

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.