Grange Castle Business Park, Clondalkin, Dublin 22
Extension of duration for a massive two-storey data centre in Clondalkin.
SD18A/0134/EP · South Dublin County Council · Lodged 14 July 2023
- Reference
- SD18A/0134/EP
- Authority
- South Dublin County Council
- Register status
- Decided
- Type
- Extension Of Duration Of Permission
- Received
- 14 July 2023
Summary
AI-generatedAn extension of duration is sought for the demolition of an existing house and construction of a 35,426 sqm two-storey data centre with a three-storey office block, 32 standby generators, and associated infrastructure at Grange Castle Business Park.
- Storeys
- 3
- Floor area
- 35,426 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- Demolition of the existing single storey house of 'erganagh' and the construction of a two storey data centre and delivery bays with associated three storey office block and services that will have a gross floor area of 35,426sq. M on an overall site of 9.2 hectares. The two storey data centre facility and delivery bay (32,419sq. M) will be separated into two adjoined blocks over two floors with a single data hall on each floor of each data centre with service and technical space around each data hall (4 data halls overall) with a two storey delivery bay attached to the east of the data centre block. A three storey office block and delivery bay (2,882sq. M) is attached to the west of the data centre block. The data centre will be served by services and plant to the north of the data centre blocks that will include 32 standby generators with 2 associated flues per generator (64 in total) and grouped into 16 towers of flour flues each (each 20m high). There are proposed to be 32 acoustically attenuated chillers located on the upper level plant gantries to the north of the data hall blocks (eight on each gantry). The development will also include a new substation with associated transformer yard and single storey transformer building (125sq. M) that will be located to the northeast of the site. The development will be accessed from the grange castle south access road from the north via the baldonnel road and will also include ancillary site development works, including 2 attenuation ponds, to connect to existing grange castle infrastructural services as well as fencing, signage, services road, entrance gate, 70 car parking spaces including 3 disabled car parking spaces, and 30 sheltered bicycle parking spaces. The development will be enclosed with landscaping to all frontages including a wetland to the west all on a site (9.2ha) located within lands in the grange castle business park south and the residential properties of erganagh, kent cottage and weston lodge on land with the townlands of aungierstown and ballybane; ballybane; and milltown and bounding baldonnel road to the west and south and grange castle south access road to the north, baldonnel, dublin
- An environmental impact assessment report (eiar) has been submitted with this application
Land-use zoning
What this land is zoned for
“To provide for enterprise and employment related uses”
National zoning type: Industrial, enterprise, employment
Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planBuilt & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Built — construction complete
A commencement notice records works starting on 25 June 2019. A completion certificate was lodged on 28 June 2021.
Notified floor area: 249 m²
2 commencement notices are linked to this development.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received14 July 2023
- Decision due7 September 2023
- Decision issued7 September 2023
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134South DublinLodged 30 Jul 2018Commercial
- GrantedAt this site
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134/EP2South DublinLodged 15 Sept 2023Industrial
- GrantedAt this site
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 —…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0295South DublinLodged 17 Feb 2021Commercial
- GrantedAt this site
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 —…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0295/EPSouth DublinLodged 2 Apr 2026Retention
- Granted130 m away
Four bedroom dormer bungalow and double garage with wastewater treatment system and associated site works
Ballybane, Baldonnell, Co. Dublin
SD03A/0358South DublinLodged 27 Aug 2003New dwelling
- Refused140 m away
Change of use of an existing two storey dwelling house of c.227sq.m. to use as an office; planning permission…
Castlebaggot, Milltown, Baldonnell, Co. Dublin.
SD09A/0124South DublinLodged 27 Mar 2009Change of use
- Refused140 m away
Change of use of an existing two storey dwelling house of c.227sq.m. to use as an office
Castlebaggot, Milltown, Baldonnell, Co. Dublin.
SD08A/0187South DublinLodged 18 Mar 2008Change of use
- Granted140 m away
Temporary change of use (for a period of 5 years) of an existing two storey dwelling house (c. 277 sq. m.) to…
Castlebaggot, Milltown, Baldonnell, Co. Dublin.
SD09A/0453South DublinLodged 25 Nov 2009Change of use
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedCommercial
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134South DublinLodged 30 Jul 2018
- GrantedIndustrial
Permission for a period of ten years for development at this site of 16.5 hectares that is located within…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0121South DublinLodged 16 Jul 2020
- GrantedRetention
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 —…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0295/EPSouth DublinLodged 2 Apr 2026
- GrantedIndustrial
Amendment and completion of the permissions granted under Reg. Ref. SD16A/0214, SD16A/0345, SD17A/0141 and…
Site within the townlands of Ballymakaily & The Grange, Newcastle Road, Lucan, Co. Dublin
SD18A/0298South DublinLodged 22 Aug 2018
- GrantedIndustrial
Construction of a two storey data centre with three storey central service spine (7,246sq.m) with plant at…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0323South DublinLodged 12 Sept 2018
- GrantedEnergy
The proposed development comprises: 1.2 no. 2 storey data centre buildings (each 16,576 sqm), which are 16m…
Woodlands & Former Diamond Innovations Site, Clonshaugh Business & Technology Park, Dublin 17
3803/20Dublin CityLodged 25 Nov 2020
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.