Planning Permission Ireland
GrantedIndustrialDecided 16 May 2022

In the townlands of Ballybane & Kilbride within Profile Park, Clondalkin, Dublin 22

Demolition of a house and construction of two data centres in Clondalkin.

SD21A/0241 · South Dublin County Council · Lodged 21 March 2022

Reference
SD21A/0241
Authority
South Dublin County Council
Register status
Appealed
Type
Permission
Received
21 March 2022
Floor area
40589 m²

Summary

AI-generated

This application seeks the demolition of an abandoned single-storey dwelling to construct two large two-storey data centres with a combined floor area of 40,589 square metres. The development includes 33 emergency generators with 22.3-metre-high flues and rooftop solar panels.

Industrialdata centredemolitionindustrialsolar
Storeys
2

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Demolition of the abandoned single storey dwelling and associated outbuilding (206sqm); construction of 2 two storey data centers with plant at roof level of each facility and associated ancillary development which will have a gross floor area of 40,589sq. M consisting of 1 two storey data center (building
  • Which will be located to the south of the site and will have a gross floor area of 24,667sq. M. Including 22 emergency generators located at ground floor level within a compound to the western side of the data center with associated flues that will be 22.3m in height; 1 two storey data center (building
  • Which will be located to the north of the site, and to the immediate north of building 11 and will have a gross floor area of 12,915sq. M including 11 emergency generators located at ground floor level within a compound to the western side of the data center with associated flues that will be 22.3m in height; each of the two data centers will include data storage rooms, associated electrical and mechanical plant rooms, loading bays, maintenance and storage spaces, office administration areas, and plant including pv panels at roof level as well as a separate house generator for each facility which will provide emergency power to the admin and ancillary spaces; each generator will include a diesel tank and there will be a refuelling area to serve the proposed emergency generators; the overall height of each data center apart from the flues and plant at roof level is c. 14.23m above the finished floor level; the overall height of each data center apart from the flues and plant at roof level is c. 14.23m above the finished floor level; single storey step-up substation (38sq. M) as well as 2 single storey switch substations (121sq. M); agi gas regulator compound that include 3 single storey buildings (134sq. M); construction of a gas powered generation plant in the form of a 13m high single storey building with a gross floor area of 2,714sq. M that will contain 10 gas generators with associated flues that will be 25m in height, and grouped in pairs and threes; the gas plant will be located to the west of building 11; ancillary site development works, that will include reorientation of the baldonnel stream, biodiversity management initiatives, attenuation ponds and the installation and connection to the underground foul and storm water drainage network, and installation of utility ducts and cables, that will include the drilling and laying of ducts and cables under the internal road network within profile park; other ancillary site development works will include hard and soft landscaping, lighting, fencing, signage, services road, entrance gates, sprinkler tanks and pump room; a temporary gas powered generation plant within a fenced yard containing 21 generator units in containers, each with associated flues (each 25m high), 12 transformers and 10 containers of controls to be located to the west of, and associated with the first phase of building 11, and will be required for a period of up to 2 years if connection to the national grid is delayed; this temporary plant will not be built if the connection to the national grid is in place prior to the operation of building 11 at this site that includes an abandoned single storey residential property on the new nangor road (r134), dublin 22; and on land within the townlands of ballybane and kilbride within profile park, clondalkin, dublin 22 on an overall site of 8.7 hectares

Land-use zoning

What this land is zoned for

EESI
To provide for enterprise and employment related uses

National zoning type: Industrial, enterprise, employment

Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 20 April 2023.

Notified floor area: 115.4

7 commencement notices are linked to this development.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Apartments 1-33, Block 8 Nangor Hall, Kilcarbery GrangeDec 2025€12,943,276244 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received21 March 2022
  2. Further information requested26 October 2021
  3. Further information received21 March 2022
  4. Decision due16 May 2022
  5. Decision issued16 May 2022
  6. Grant issued19 July 2022
  7. Appeal submitted13 June 2022
  8. Appeal decided6 July 2022
  9. Permission expiry13 October 2022

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.