Belgard Road, Belgard Square East, Blessington Road, Tallaght, Dublin 24
A mixed-use development featuring 310 build-to-rent apartments, a creche, and commercial units.
SHD3ABP-313760-22 · South Dublin County Council · Lodged 9 June 2022
- Reference
- SHD3ABP-313760-22
- Authority
- South Dublin County Council
- Register status
- Decided
- Type
- SHD3-Application to ABP
- Received
- 9 June 2022
Summary
AI-generatedAn application for a strategic housing development consisting of 310 build-to-rent apartments across three blocks ranging from 6 to 12 storeys. The development also includes a creche, 10 commercial units, communal amenity spaces, and a basement level.
- Residential units
- 310
- Storeys
- 12
- Floor area
- 2,289 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Mixed-use development including 310 "build-to-rent" residential apartments, a creche and a number of commercial units (c. 2,289 sqm) on a c. 1.26 ha site; consisting of the demolition of existing boundary wall and construction of: c. 2,289 sqm of retail/commercial floor space across 10 units including retail, restaurant/café and class 2 financial/professional services and office use, and a crèche (257sqm) at ground and first floor levels; 310 build to rent residential apartments including 99 one bedroom units, 203 two bedroom units and 8 three bedroom units within a part 6 to part 12 storey development across 3 blocks over partial basement; c. 2,223 sqm of communal external amenity space provided in the form of a ground floor garden and external terraces at fifth, sixth, seventh and eighth floor levels; c. 1,026 sqm of public open space provided in the form of a central courtyard with landscaped areas at site perimeters; c. 1,785 sqm of resident support facilities and services and amenities provided at basement, ground and first floor levels; vehicular access to the basement development from a new access point at belgard square east; a new tertiary route provided in the southern part of the site linking belgard square east and belgard road; provision of 130 car parking spaces (including 8 club car spaces and 6 disabled access spaces) at basement level in addition to 5 set down spaces (4 serving creche) and 1 disabled access space at ground level, layby on belgard square east, 6 motorcycle spaces and a total of 763 bicycle parking spaces; provision of 4 ø0.3m microwave link dishes to be mounted on 2 steel support pole affixed to lift shaft overrun, all enclosed in radio friendly grp shrouds, together with associated equipment at roof level at block b; provision of 3 esb substations with switch rooms and plant rooms at basement level, hard and soft landscaped areas, bin and bicycle stores, public lighting, attenuation, green roof, plant at roof level, service connections and all ancillary site development works. The application contains a statement setting out how the proposal will be consistent with the objectives of the relevant development plan and local area plan. The application contains a statement indicating why permission should be granted for the proposed development, having regard to a consideration specified in section 37(2)(b) of the planning and development act, 2000, as amended, notwithstanding that the proposed development materially contravenes a relevant development plan or local area plan other than in relation to the zoning of the land.
Land-use zoning
What this land is zoned for
“To protect, improve and provide for the future development of Town Centres”
National zoning type: City/Town/village Centre, central area
Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planBuilt & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Recent sales nearby
within 500 m| Address | Date | Price | Distance |
|---|---|---|---|
| 72 Abberley Sq, Belgard Rd, Tallaght Dublin 24 | Sept 2025 | €210,000 | 120 m |
| 98 Abberley Sq, Belgard Rd, Tallaght Dublin 24 | Oct 2025 | €255,000 | 120 m |
| 91 Abberley Sq, Belgard Rd, Tallaght Dublin 24 | Oct 2025 | €255,000 | 120 m |
| 27 Abberley Square, Tallaght, Dublin 24 | Mar 2025 | €283,000 | 120 m |
| Apt 62, Tuansgate, Belgard Sq East Dublin 24 | Nov 2025 | €310,000 | 125 m |
| 49 Tuansgate, Belgard Sq, Tallaght Dublin 24 | Jul 2025 | €215,000 | 125 m |
| 26 Tuansgate, Belgard Sq East, Tallaght Dublin 24 | Jul 2025 | €283,000 | 125 m |
| 48 The Crescent, Stonehaven, Blessington Roadprice excludes VAT | Nov 2025 | €480,176 | 139 m |
Nearby properties, not this site — a guide to local values.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received9 June 2022
- Decision due3 August 2022
- Decision issued11 June 2025
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
The proposed development principally comprises: the demolition and removal of existing boundary walls and…
A site of approximately 1.19 Ha at Belgard Square East, Belgard Road and Old Blessington Road, Tallaght, Dublin 24
LRD25A/0009WSouth DublinLodged 19 Nov 2025Apartments
- GrantedAt this site
Construction of a retail unit, a class II, two storey retail unit, storage and two storey creche at ground…
Site at the junction of, The Belgard Road And, Blessington Road, Tallaght, Dublin 24
SD04A/0975/EPSouth DublinLodged 7 Mar 2013Apartments
- GrantedAt this site
Construction of a retail unit, a class II, two storey retail unit, storage and two storey creche at ground…
Site at the junction of, The Belgard Road And, Blessington Road, Tallaght, Dublin 24
SD04A/0975South DublinLodged 4 Jan 2006Apartments
- GrantedAt this site
The construction of a 5 storey over basement level car park mixed use development of 26915sq.m. gross floor…
Belgard Square East, Tallaght, Dublin 24
SD09A/0419South DublinLodged 22 Jan 2010Commercial
- GrantedAt this site
The construction of a 5 storey over basement level car park mixed use development of 26915sq.m gross floor…
Belgard Square East, Tallaght, Dublin 24
SD09A/0419/EPSouth DublinLodged 21 Jan 2015Commercial
- Granted40 m away
An above ground natural gas pressure reduction unit measuring 1.42m x 0.51m x 1.8m (L x W x H) and a 3m high…
Dockfield DRI, Belgard Road, Dublin 22
SD16A/0195South DublinLodged 29 Jul 2016Infrastructure
- Granted80 m away
New external signage fixed at high level to the south elevation; new 2,100mm high totem/banner directory sign…
1, Tuansgate, Belgard Square East, Tallaght, Dublin 24
SD19A/0191South DublinLodged 14 Jun 2019Commercial
- Granted100 m away
Change of use from existing commercial premises to proposed 707sq.m. "Sams" kids entertainment centre, with…
Unit 3, Block 2, Tallaght Retail Centre, Belgard Road, Tallaght, Dublin 24
SD09A/0069South DublinLodged 13 May 2009Change of use
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- RefusedApartments
On a site bound by Belgard Road (R113) to the east, Belgard Square North to the North, Belgard Square East to…
The Former ABB Site, Belgard Road, Tallaght, Dublin 24
SHD3ABP-313606-22South DublinLodged 18 May 2022
- GrantedApartments
Development consisting of (1) The demolition of the upper level retail units and the open air carpark deck…
Block One, Tallaght Retail Centre, Belgard Road, Dublin 24
SD03A/0801South DublinLodged 26 Feb 2004
- RefusedApartments
(i) Demolition of the existing industrial and commercial buildings (15,989sq.m); (ii) construction of a…
Lands to the west of Old Belgard Road and north, south and west of Cookstown Road, Cookstown Industrial Estate, Dublin 24
SHD3ABP-309731-21South DublinLodged 19 Mar 2021
- GrantedApartments
Demolition of the existing industrial and commercial office buildings totalling c.4,628sqm; Construction of a…
Glen Abbey Complex, Belgard Road, Cookstown Industrial Estate, Dublin 24, D24 W2XA
SHD3ABP-309916-21South DublinLodged 9 Apr 2021
- RefusedApartments
Mixed residential and commercial development (GFA 38,207.1sq.m) providing a total of 246 apartments in 2…
Site located at Units 60, 66, 67 Fourth Avenue, And Sites 69 & 70 Cookstown Road, As well as vacant lands, Cookstown Industrial Estate, Tallaght, Dublin 24
SD16A/0270South DublinLodged 29 Jul 2016
- GrantedApartments
Construction of a retail unit, a class II, two storey retail unit, storage and two storey creche at ground…
Site at the junction of, The Belgard Road And, Blessington Road, Tallaght, Dublin 24
SD04A/0975/EPSouth DublinLodged 7 Mar 2013
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.