Planning Permission Ireland
RefusedIndustrialDecided 30 July 2024

Mountkennedy Demesne & Tinnapark Demesne, Co. Wicklow

Extension of duration for an access road and 10 two-storey data centre units.

24306 · Wicklow County Council · Lodged 8 July 2024

Reference
24306
Authority
Wicklow County Council
Register status
Decided
Type
EXTENSION OF DURATION
Received
8 July 2024

Summary

AI-generated

An extension of duration is sought for a development comprising a 1.1km access road with cycle tracks and footpaths, alongside 10 identical two-storey data centre units. The project also involves modifications to a demesne wall and closure of an access to a protected structure.

Industrialdata centreinfrastructureextension of duration
Storeys
2

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Section 42(1) on prr 10/2123 (access road from the south western roundabout of the ballyronan interchange to the site entrance. The road continues northward for an additional c 0.3km terminating in a cul de sac formed by bollards at its junction with the laneway located at the northern site boundaries (total road length c 1.1km). The proposed road will include a two way cycle track and a footpath and will involve restoration / modification of the existing demesne wall; closure of the existing left in / left out access to mountkennedy house (protected structure) off the n
  • Access will be provided to the existing laneway directly from the proposed access road, 10 no identical two storey data centre units each measuring c 10,915 sqm gross. The ground floor of each unit comprises plant areas, storage, workshops, reception / lobby, office space, inspection area, breakroom, internal loading areas and circulation space. The first floor of each unit comprises a net technical area, offices, ancillary plant, storage and circulation space. Each data centre unit will also have an ancillary service yard that will incorporate a sprinkler tank, a pump house, an mv switchroom, esb switch rooms, electrical transformers enclosed within a post and wire mesh fence and a fuel storage tank, an auxillary cooling compound located to thee rear of each building and adjacent to the service yard, an enclosed electrical compound located centrally along the southern site boundary providing for a future step down transformer from the existing 220/110kv overhead power line, a primary dry cooling compound in area housing dry cooling units located to the west of the site; 3 no heat exchanger buildings located on site at the south west corner, north west corner and to the south of the site entrance at the eastern boundary, 250 car parking spaces including 40 electric car parking spaces and 20 disabled car parking spaces; a temporary waste water treatment plant and percolation area located centrally within the site; 1 main security hut located at the site entrance and 10 individual security huts located at the entrance to each individual data centre unit; landscape berming and additional planting at the site boundaries; all ancillary site developments works. The proposed development comprises or is for the purposes of an activity that may require an integrated pollution prevention control licence and has a total gross floor area of 111,228 sqm)

Key dates

Timeline

  1. Application received8 July 2024
  2. Decision due1 September 2024
  3. Decision issued30 July 2024

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.