In the Townlands of Kilbane Killeagy (Ryan) Shannaknock, Killeagy (Stritch) Killeagy (Goonan) Ballymoloney, Magherareagh and Lackareagh Beg Co. Clare.
Construction of a seven-turbine wind farm with a maximum tip height of 180 metres and an electrical substation.
2460411 · Clare County Council · Lodged 29 August 2024
- Reference
- 2460411
- Authority
- Clare County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 29 August 2024
Summary
AI-generatedThe development will consist of seven wind turbines with a tip height range of 179.5m to 180m. It also includes a 38kV electrical substation, a battery energy storage system, a permanent meteorological mast, and associated site works.
- Storey
- 1
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- The development will consist of: (i) the construction of 7 no. Wind turbines with the following parameters: a. Total tip height range of 179.5m
- 180m, b. Rotor diameter range of 149m
- 155m, c. Hub height range of 102.5m to 105m, (ii) construction of associated foundations, hardstand and assembly areas; (iii) all associated wind farm underground electrical and communications cabling connecting the turbines and mast to the proposed electrical substation; (iv) construction of 1 no. Permanent 38kv electrical substation including a single-story control building with welfare facilities, all associated electrical plant and equipment, security fencing, entrance on to new access road, all associated internal underground cabling, drainage infrastructure, wastewater holding tank, retention separator tank, and all ancillary works, in the townland of killeagy (goonan), co. Clare; (v) a battery energy storage system within the 38kv electrical substation compound; (vi) 1 no. Permanent meteorological mast of c. 36.5m in height, associated foundation and hard-standing area in the townland of shannaknock; (vii) the permanent upgrade of 1 no. Existing site entrance off the l7080 (‘the gap road’) for the provision of construction and operational access; (viii) provision of 3 no. New permanent site entrances off the l7080 for the provision of construction and operational access; (ix) provision of 3 no. New temporary site entrances off the l7080 for the provision of construction access; (x) upgrade of existing tracks/ roads, including the l7080, and the provision of new site access roads, 4 no. Watercourse crossings, junctions and hardstand areas; (xi) 1 no. Temporary construction compound with temporary offices and staff facilities in the townland of killeagy (goonan); (xii) 1 no. Temporary storage area in the townland of killeagy (goonan); (xiii) 1 no. Borrow pit in the townland of killeagy (goonan); (xiv) peat and spoil management; (xv) tree felling to accommodate the construction and operation of the proposed development; (xvi) operational stage site and amenity signage; and (xvii) all ancillary apparatus and site development works above and below ground, including soft and hard landscaping and drainage infrastructure. A 10-year planning permission and 35-year operational life of the wind farm from the date of commissioning of the entire wind farm is sought. A design flexibility opinion issued by clare county council on 22nd april 2024 accomanies this application. The de
Key dates
Timeline
- Application received29 August 2024
- Decision due23 October 2024
- Decision issued23 October 2024
- Grant issued12 September 2025
- Appeal submitted19 November 2024
- Appeal decided11 July 2025
- Permission expiry11 September 2035
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
A ten-year planning permission for development at a site in the townlands of Kilbane, Killeagy (Ryan),…
Kilbane Killeagy (Ryan) Shannaknock Killeagy (Stritch) , Killeagy (Goonan) Ballymoloney Magherareagh and Lackareagh Beg , Co. Clare.
2460394ClareLodged 21 Aug 2024
- GrantedEnergy
Nineteen (19) number wind turbines (blade tip height up to 169 metres), Nineteen (19) number wind turbine…
Ballydonaghan Caherhurley Coumnagun , Carrownagowan Inchalughoge , Killokennedy Kilbane
229000ClareLodged 30 Nov 2020
- Awaiting decisionEnergy
For development of a wind farm in the townlands of Fahy Beg, Fahy More North, Ballymoloney, Ballyknavin (Ed…
Fahy Beg Fahy More North Ballymoloney Ballyknavin (Ed O'Briensbridge) Ballyquin More , Woodpark Leitrim Fahy More South Ballybrack Aharinaghmore Tooreen , (Ed Cloghers) Aharinaghbeg Knockdonagh Roo East Blackwater Rosmadda West Parkroe Lackyle (Ed
2317ClareLodged 13 Jan 2023
- RefusedEnergy
For a period of 10 years for a development consisting of the provision of the following: i. 8 no. wind…
Gannow Attimonmore South Attimonbeg Attimonmore North Ballynanulty etc. (See Notices) , Co. Galway
2561412galwayLodged 29 Sept 2025
- RefusedEnergy
For a renewable energy development in the townlands of Moanmore Lower, Moanmore South, Tullabrack, Tullabrack…
Moanmore Lower Moanmore South Tullabrack Tullabrack East and Gower South , Kilrush , Co. Clare
2560257ClareLodged 8 May 2025
- RefusedEnergy
We, Cunlaghfadda Green Energy Limited, intend to apply for a ten-year planning permission for development in…
Townlands of Knockroe , Cunlaghfadda Harefield Cloonbaul and Knockaunakill , County Mayo.
2660398MayoLodged 20 May 2026
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.