30 Earlsfort Terrace/Department of Foreign Affairs Laneway, Dublin 2
Construction of a new ESB substation, bicycle parking, and changing facilities following demolition of a bike shed.
3611/23 · Dublin City Council · Lodged 20 April 2023
- Reference
- 3611/23
- Authority
- Dublin City Council
- Register status
- Decided
- Type
- Local Authority Works
- Received
- 20 April 2023
Summary
AI-generatedLocal authority works are proposed to construct a single-storey ESB substation with a switch room, covered bicycle parking, and changing facilities. The project involves the demolition of an existing non-historic bicycle shed near several protected structures.
- Storey
- 1
- Floor area
- 98 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- Saw: in accordance with part 9 of s. I. No. 600/2001, planning and development regulations 2001 (as amended), proposed to construct a new single storey esb substation with switch room and covered bicycle parking area with changing facilities at no. 30 earlsfort terrace/department of foreign affairs laneway, dublin
- The proposed development will consist of : (a) the construction of a new single storey esb substation with switch room and covered bicycle parking area with changing facilities, external lighting an all associated site works. The total floor area of the development is c. 98m2. (b) demolition of an existing non-historic, single storey bicycle shed. The national concert hall, real tennis court and iveagh house (department of foreign affairs) and iveagh gardens, including stone garden folly are designated protected structures (reference rps 2425, 2426 and 7791). The development has been screened for both appropriate assessment and environmental impact assessment. The screening assessment process concluded that the proposed development does not require an appropriate assessment or the preparation of a natural impact assessment. It is considered that the proposed development is sub-threshold for the purposes of an eia and is therefore no mandatory requirement to prepare an eiar. Any person may, within 4 weeks from the date of the notice, apply to an bord pleanala for a screening determination as to whether the development would be likely to have significant effects on the environment. The above mentioned screenings may be inspected on line within 3 working days of the publication of the newspaper notice at the following website: https://www. Gov. Ie/en/consultions drawings and particulars of the proposed development will be available for inspection by appointment only and within two working days notice, between 10.00am and 12.30pm and between 2.30pm and 4.00pm, monday to friday (excluding public holidays) for a period of 6 weeks beginning on the date of publication of this notice at : the office of public works, head office, jonathan swift street, trim, co. Meath, c15 nx36 and the office of public works (major projects), 1gq, george's quay , dublin 2, d02 yo98. All appointments for viewing should be sent to email: ncs@opw. Ie or tel: 046 9422813 submissions and/or observations with respect to the proposed development, dealing with the proper planning and development of the area in which the development is situated, may be made in writing within a period of 6 weeks beginning on 19 april 2023: the commissioners of public works in ireland, office of public works (major projects), 1gq georges quay, dublin 2, d02 y098
Key dates
Timeline
- Application received20 April 2023
- Decision due23 May 2023
- Decision issued23 May 2023
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
SAW: The Commissioners of Public Works in Ireland for and on behalf of The Courts Service, In accordance with…
The Dublin Family Courts, located between Hammond Lane, Church Street and Bow Street, Dublin 7
4911/23Dublin CityLodged 4 Dec 2023
- GrantedInfrastructure
PROTECTED STRUCTURE: Permission for development at this site which extends from North Wall Quay Extension to…
Dublin Port, Alexandra Road, Dublin 1
3220/21Dublin CityLodged 27 Jul 2021
- Awaiting decisionInfrastructure
SAW: PROTECTED STRUCTURE: The development will consist of the replacement of existing non historic perimeter…
Rear of 52 St. Stephen's Green at 6 Ely Place Upper, Dublin, 2
3494/25Dublin CityLodged 17 Dec 2025
- Awaiting decisionInfrastructure
SAW: Part 9 Planning and Development Regulations 2001 S.I. 600/2001 The Commissioners of Public Works in…
An Garda Síochána, 43, Donnybrook Garda Station, Donnybrook Road, Dublin 4
4209/24Dublin CityLodged 28 Aug 2024
- Awaiting decisionInfrastructure
PART 9 PLANNING AND DEVELOPMENT REGULATIONS 2001 SI. 600/2001 THE COMMISSIONERS OF PUBLIC WORKS IN IRELAND In…
Swords Garda Station, Main St, Swords, Co Dublin, K67 RF70
PARTIX/002/24FingalLodged 4 Jul 2024
- Awaiting decisionInfrastructure
SAW: PROTECTED STRUCTURE: In accordance with the provisions of Part 9 of S.I. No. 600/2001, Planning and…
Dublin Castle, Castle Street, Dublin 2
5110/26Dublin CityLodged 22 Apr 2026
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.