Planning Permission Ireland
GrantedInfrastructureDecided 21 January 2020

Terminal 4 North Lands, Dublin Port, Dublin 1, bounded by Bond Road, Tolka Quay Road & Promenade Road

Demolition of ten buildings at Dublin Port to create a multi-functional storage yard with high-mast lighting.

4483/19 · Dublin City Council · Lodged 18 November 2019

Reference
4483/19
Authority
Dublin City Council
Register status
Appealed
Type
Permission
Received
18 November 2019

Summary

AI-generated

The development consists of the demolition of ten redundant buildings totaling approximately 6,830 sq.m and general site clearance. The site will be optimized as a multi-functional storage yard, primarily for heavy goods vehicles, featuring new check-in booths, security fencing, and 30m high lighting columns.

Infrastructureportdemolitionindustrial

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The proposed development will consist of the demolition of 10 no. Redundant buildings (c. 6830sqm) and removal of temporary structures including portacabins and general site clearance (an existing substation and pump house will remain in situ) to optimise the use of the site as a multi-functional storage yard (primarily for heavy goods vehicles) and facilitate wider infrastructural upgrades to provide additional capacity within the port. The proposed development will also include: construction of vehicular check-in booths (c. 30sqm); an open-air blockwork electrical enclosure; amendments to boundary treatments including provision of 4m high security fencing (including 1.5m high retaining walls) on the northern, eastern and southern boundaries; 4m high security fencing fixed to the existing masonry wall along the western boundary with bond road; 3 no. New 12m wide automatic vehicular sliding gates and re-building of 1 no. Existing 9m wide automatic vehicular sliding gate; provision of 14 no. High mast lighting columns (30m high) and 54 no. Perimeter lighting columns (12m high); installation of 9 no. Cctv columns (18m high); installation of new pavement, underground drainage, attenuation, interceptors, water services and electrical infrastructure; installation of new wash bay and fuel spill areas; installation of pedestrian barriers; and all associated site and development works on a site of c. 9.52ha.

Land-use zoning

What this land is zoned for

Z7: Employment (Heavy)SI
To provide for the protection and creation of industrial uses, and facilitate opportunities for employment creation including Port Related Activities.

National zoning type: General industry

Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
95 Merchants Rd, East Wall, Dublin 3Oct 2025€343,366477 m
75 Merchants Rd, East Wall, Dublin 3May 2026€330,000494 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received18 November 2019
  2. Decision due21 January 2020
  3. Decision issued21 January 2020
  4. Grant issued25 August 2020
  5. Appeal submitted17 February 2020
  6. Appeal decided25 August 2020

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.