Planning Permission Ireland
GrantedInfrastructureDecided 26 October 2023

ESB Belcamp 220 kV Substation, in the townlands of Clonshaugh and Belcamp, Co. Dublin

New electricity transmission infrastructure at the ESB Belcamp substation.

F23A/0040 · Fingal County Council · Lodged 1 September 2023

Reference
F23A/0040
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
1 September 2023

Summary

AI-generated

The development consists of major new electricity transmission infrastructure at the existing ESB Belcamp 220 kV substation. It includes a new 17-meter-high Gas Insulated Switchgear building, three transformers, a STATCOM transformer, and seven lightning protection masts.

Infrastructuresubstationgridinfrastructure
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • The development will consist of the provision of new electricity transmission infrastructure at the existing esb belcamp 220 kv substation, comprising
  • Installation of an additional 220 kv gas insulated switchgear (gis) 16 bay building north of the existing station compound (approximately 84 m by 25m and 17 m in height), this includes an associated extension to the hardstanding compound {approximately 3.2 hectares) to facilitate the same. This includes: a) three 220/110 kv transformers located adjacent to the new 220 kv gis building (approximately 8m high); b) a busduct connection from the new 220 kv gis building to the existing 220 kv belcamp substation; c) one +100 mvar220 kv statcom transformer including associated auxiliary transformer, series coils, outdoor cooling bank control and valve building
  • Seven lightning protection masts (ranging in height from approximately 8 m to 20 m)
  • All ancillary site development works including site preparation works, site clearance and levelling; provision of hardstanding, internal access tracks and temporary construction compound; associated underground cabling and earthgrid; associated extended surface water drainage network including attenuation storage; associated reinforced concrete perimeter wall (3 m in height with a 1 m electric fence on top); perimeter palisade fencing (3 m in height), external lighting as required to facilitate the development
  • Access to the proposed development site will be via the existing internal access road, and existing vehicular entrance onto the r139 regional road. A natura impact statement (nis) accompanies this application. Ai received 01/09/23

Land-use zoning

What this land is zoned for

HT - High TechnologyCOE
Provide for office, research and development and high technology/high technology manufacturing type employment in a high quality built and landscaped environment

National zoning type: Office, business/technology park and related

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received1 September 2023
  2. Decision due26 October 2023
  3. Decision issued26 October 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.