GrantedCommercialDecided 30 October 2025

Former Clyde House, IDA Blanchardstown Business & Technology Park, Snugborough Road, Blanchardstown, Dublin 15

Extension of duration and modifications to a business park development in Blanchardstown.

FW21A/0176/E1A · Fingal County Council · Lodged 9 September 2025

Reference
FW21A/0176/E1A
Authority
Fingal County Council
Register status
Decided
Type
Extension Of Duration Of Permission
Received
9 September 2025

Summary

AI-generated

The application seeks an extension of duration and revisions to permitted plans at the former Clyde House. Changes include ground floor extensions, a link bridge, roof plant alterations, canopy installations, and modifications to gas generator flues and screening.

Commercialbusiness parkextension of durationmodifications

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • The development will consist of revisions to parent permission fcc reg. Ref. Fw20a/0087 and modifications permitted under fcc reg. Ref. Fw21a/0073 to include the following
  • Ground floor extensions to permitted building db6x (formerly known as building no
  • To include stairs and provision of a link bridge connecting with db7x (formerly known as building no
  • To the north east. Alterations to existing stairs at db6x
  • Alterations to the plant/roof area of db7x at first and roof level to include changes to the gantry platform and screen height reduction, provision of new pprs/pcrs and a new cooling tower
  • Provision of canopies at ground floor level to building db5x, db6x and db7x
  • Reduction in height of 9 no. Permitted flues associated with the gas generators from c. 18m to c. 15m high and an increase in internal flue diameter from c. 2.2m to c. 2.5m. Reduction in height of external screening (c. 8m) to the gas generator compound and estate road south of the subject site. Provision of screening to permitted switchroom building
  • Removal of 1 no. Permitted salt saturator tank
  • Provision of a raised ramped pedestrian crossover and relocation of 2 no. Permitted parking spaces. No change to the permitted quantum of car and bicycle parking
  • All associated site development works, services provision, drainage works, minor amendments to boundary treatments to include a relocated fence to the east of db7x and provision of security fencing to the gas generator compound. No works are proposed to the existing telecommunication pylon and overhead lines running diagonally through the site from south west to north east
  • The total gross internal floor area of the development including data halls and ancillary structures is increased to c. 19,114sqm from c. 19,040sqm under fcc reg. Ref. Fw21a/0073
  • All other development as permitted under fcc reg. Refs. Fw20a/0087 and fw21a/0073
  • A permitted 110kv substation (under construction) located to the south east of this site was subject of a separate strategic infrastructure development application to an bord pleanála (abp ref. 307296-20) under section 182a of the planning and development act 2000 (as amended)

Key dates

Timeline

  1. Application received9 September 2025
  2. Decision due3 November 2025
  3. Decision issued30 October 2025
  4. Permission expiry1 January 2031

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.