Planning Permission Ireland
GrantedIndustrialDecided 25 April 2023

Site fronting Damastown Road & Damastown Green, Damastown, Mulhuddart, Dublin 15

Construction of a large medical devices manufacturing facility with offices, warehousing, and ancillary structures.

FW22A/0319 · Fingal County Council · Lodged 10 March 2023

Reference
FW22A/0319
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
10 March 2023

Summary

AI-generated

The development consists of a 16,805 sq. m. medical devices manufacturing facility with associated warehousing and a three-storey office block. The site will also feature 120 car parking spaces, 10 materials silos, an ESB substation, and other ancillary structures.

Industrialmanufacturingmedicalindustrial
Storeys
3
Floor area
16,805 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Construction of a 16,805 sq. M. (gfa) medical devices manufacturing facility with associated ancillary warehousing and a three storey office/administration block; 120 no. Surface car parking spaces (incl. 7 no. Disabled parking spaces and 12 no electric charging spaces); 40 no. Cycle parking spaces (incl. 6 no. E-bike parking spaces); 12 no. Motorcycle parking spaces; building and site signage and 3 no. Flagpoles
  • Construction of ancillary buildings and structures including: 2 no. Single storey security huts, an esb substation and mv room, 4 no. Condenser unit enclosures, a sprinkler water storage tank and pumphouse building, 10 no. Materials silos and 6 no. Loading docks
  • All other associated site works required to facilitate the proposed development including: formation of vehicle accesses onto damastown road and onto damastown green, provision of a pedestrian footpath and landscaping along damastown road across the length of site boundary to the junction with damastown green; ground levelling and landscaping on the eastern side of damastown green along the length of site boundary to the junction with damastown road; construction of dished pedestrian crossing (with tactile paving) at the existing footpath to the west of damastown green; boundary enclosure/fencing and site landscaping: and the installation of a surface water pipe from the site to an existing manhole on lands to the east. I a natura impact statement (nis} will be submitted to the planning authority with the application, and the nis will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the offices of the planning authority. Ai received 10/03/23

Land-use zoning

What this land is zoned for

GE - General EmploymentSI
Provide opportunities for general enterprise and employment

National zoning type: Industrial, enterprise, employment

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 21 October 2023. A completion certificate was lodged on 3 April 2025.

Notified floor area: 12.8

4 commencement notices are linked to this development.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
27 The Grove, Pheasant Run, Clonee Dublin 15Apr 2025€505,000432 m
42 The Grove, Pheasant Run, Littlepace Dublin 15Mar 2025€445,000460 m
10 The Park, Pheasant Run, CloneeJul 2025€485,000488 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received10 March 2023
  2. Decision due4 May 2023
  3. Decision issued25 April 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.