Planning Permission Ireland
GrantedRetentionDecided 29 February 2024

A site at Orion Business Park, North-West Business Park, Ballycoolin, D15XE2N

Retention of a new 500KVA substation and back-up generator at Orion Business Park.

FW24A/0012 · Fingal County Council · Lodged 12 January 2024

Reference
FW24A/0012
Authority
Fingal County Council
Register status
Decided
Type
Retention
Received
12 January 2024

Summary

AI-generated

The application seeks retention permission for a newly constructed 500KVA substation with a gross floor area of 30.1 square meters and a maximum height of 3.2 meters, along with a back-up generator. The development also includes amendments to previously permitted applications to incorporate these works.

Retentionsubstationindustrialretention
Floor area
30 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The application for retention consists of construction of a new 500kva substation (gfa of 30.1 sqm & max height of 3.2 m) and back-up generator. The development will also include amendement to permission ref. Fw17a/0167 and permission ref. Fw18a/0114 to include the works subject to retention.

Key dates

Timeline

  1. Application received12 January 2024
  2. Decision due7 March 2024
  3. Decision issued29 February 2024

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.