Planning Permission Ireland
GrantedIndustrialDecided 12 February 2025

Orion Business Park, North West Business Park, Ballycoolin, Dublin 15, D15 XE2N

Amendments to a permitted data centre development in Ballycoolin, including a new battery storage system.

FW24A/0532E · Fingal County Council · Lodged 16 December 2024

Reference
FW24A/0532E
Authority
Fingal County Council
Register status
Decided
Type
Permission
Received
16 December 2024

Summary

AI-generated

The application seeks modifications to a previously permitted data centre scheme. Changes include a new Battery Energy Storage System (BESS) with a raised platform, a 500mm height increase to one building, new steel stair towers, and additional plant housing.

Industrialdata centrebessenergyindustrial
Floor area
15 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • The application for permission consists of amendments to permission reg. Ref. Fw17a/0167 as amended by permission reg. Refs. Fw18a/0114, and fw24a/0246e accounting for various amendments to the permitted 3 no. Data centres, associated infrastructure and associated works. The proposed modifications will comprise the following
  • Revised layout for southwest corner of the site to provide for a battery energy storage system (bess) with raised platform and screening, and modifications to the permitted concrete surface and landscaping to allow for same
  • 500mm increase in the building height of the permitted mv2 building
  • Modification of stair access to the permitted fuel & urea tanks by way of addition of 2 no. Steel stair towers
  • Addition of plant housing between the csb building and fuel tanks of c. 15 sq m and height of c. 3.7m
  • Change in height of flue sampling platforms at each of the 3 no. Flue groups by 800mm; and
  • All associated works ancillary to the modifications. The application relates to a development for the purposes of an activity requiring an industrial emissions licence and epa-industrial emissions directive (ie) licence (epa reg no. P1210-01) has been applied for in relation to the activity at the development site

Land-use zoning

What this land is zoned for

HT - High TechnologyCOE
Provide for office, research and development and high technology/high technology manufacturing type employment in a high quality built and landscaped environment

National zoning type: Office, business/technology park and related

Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Key dates

Timeline

  1. Application received16 December 2024
  2. Decision due18 February 2025
  3. Decision issued12 February 2025

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.