The route alignment is 3.9km in length running from the, Existing Green Line Terminus at Broombridge to a new terminus at Charlestown, primarily located, Within the adminsitrative area of Dublin City Council (DCC) with the exception of the, Proposed Charl
A proposed 3.9km Luas light rail extension from Broombridge to Charlestown.
SID/07/24 · Fingal County Council · Lodged 18 November 2024
- Reference
- SID/07/24
- Authority
- Fingal County Council
- Register status
- In progress
- Received
- 18 November 2024
Summary
AI-generatedThe proposed scheme extends the Luas Green Line by 3.9km, crossing the Maynooth railway line, Royal Canal, and Tolka River via new bridges. It includes enlarging the Hamilton Depot, constructing new tracks, and routing through Tolka Valley Park and local roads to a new terminus at Charlestown.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
The route alignment is 3.9km in length running from the existing green line terminus at broombridge to a new terminus at charlestown, primarily located within the administrative area of dublin city council(dcc) with the exception of the proposed charlestown terminus, which isin the administrative area of fingal county council (fcc). The proposed scheme starts at the existing luas stabling area just south of the current broombridge stop where the hamilton depot will be enlarged with the addition of four new track lines in order to accommodate an increase in light rail vehicle (lrv) storage. The track alignment will cross over the existing iarnród éireann maynooth line and royal canal via a bridge structure, continue along broombridge road, cross the tolka river via another bridge structure and continue through tolka valley park. The alignment will cross tolka valley road and continue along the former finglaswood stream valley to arrive at st helena’s stop before crossing to farnham pitches which will be modified to accommodate the scheme. The line will continue through the park and cross wellmount road into patrickswell place, where the existing access road will be realigned. The alignment will proceed between the existing ravens court development and finglas garda station to arrive at finglas village stop. The line will then run parallel to the n2 road before crossing the existing roundabout which will be replaced with an at grade signalised junction. A multi-storey park and ride structure will be constructed in this area. The alignment will then turn onto st margaret’s road where the st margaret’s stop will be located. The route will continue northwards before arriving at the charlestown terminus where the existing junction with melville road will be reconfigured. Abp ref: 321278-24 website:www. Luasfinglasro. Ie
Key dates
Timeline
- Application received18 November 2024
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
An Bord Pleanála Ref. No. ABP-314724-22 Website www.metrolinkro.ie The works will generally comprise but are…
Estuary through Swords, Dublin Airport,, Ballymun, Glasnevin and the City Centre to Charlemont, in the south of Dublin City Centre,, Co. Dublin
SID/02/22FingalLodged 19 Aug 2024
- GrantedInfrastructure
Dodder Greenway Route Scheme comprising: The proposed Dodder Greenway is being developed to be a Greenway of…
Dodder Greenway Route Scheme
SD178/0003South DublinLodged 22 Jun 2017
- GrantedInfrastructure
[SDZ04A/3 forms part of this application]. Construction of the Adamstown Link Road linking the proposed…
Lands bounded generally by the, Outer Ring Road To The East The Dublin-Kildare, Rail Line To The South, The Griffeen Housing Development, To The North, And Adamstown Strategic Development Zone, To The West In The Town Lands Of, Adamstown, Kishogue And, Ba
SD04A/0964South DublinLodged 23 Dec 2004
- GrantedInfrastructure
The development will consist of works located inside the Clonburris SDZ relating to the Stage 2 roads, public…
Within the townlands of Kishoge, Balgaddy, Neillstown and Cappagh, Clondalkin & Lucan, Dublin 22
SDZ24A/0033WSouth DublinLodged 6 Dec 2024
- GrantedInfrastructure
In accordance with Section 37E of the Planning and Development Act 2000, as amended, Irish Water gives notice…
County Fingal & County Dublin
ABP-312131-21South DublinLodged 2 May 2024
- InvalidInfrastructure
Permission for construction of a temporary bus depot to facilitate the temporary storage, maintenance and…
Former Mouldpro International Site , Jamestown Road & Poppintree Park Lane West, Finglas, Dublin 11
4347/22Dublin CityLodged 29 Jun 2022
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.