KILPADDOGE, TARBERT, CO KERRY
Development of a synchronous compensator compound, 220kV substation, and battery storage facility in Tarbert.
21549 · Kerry County Council · Lodged 25 May 2021
- Reference
- 21549
- Authority
- Kerry County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 25 May 2021
Summary
AI-generatedThis major energy infrastructure project includes a High Inertia Synchronous Compensator (HISC) compound with a 12.1m high structure, a 220kV Gas Insulated Switchgear (GIS) substation building up to 13.2m high, and a battery storage compound containing 5 battery containers and associated equipment.
- Storey
- 1
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
(a) a high intertia synchronous compensator (hisc) compound containing 1 no. Hisc unit enclosed within a steel clad framed style structure (12.1m max height) and suppported by 8 no. Electrical equipment containers (containing ancillary power supply products including a static fequency converts, mv switchgear, exciters, lv distribution, control room, welfare and office), main auxiliary and start-up electrical transformers, generator circuit breaker, switchgear equipment, external cooler units and 1 no. Back up diesel generator and associated diesel storage tank; (b) a 220kv high voltage gas insultated switchgear (gis) substation compound containing a gis substation building with all control and hv equipment within a single storey building (13.2m max height). The building will be surrounded by a compound road and contained within a 2.6m high galvanised steel palisade fence; (c) a battery storage compound containing 5 no. Battery storage containers, enclosed in steel containers of dimensions approximately 13m by 2.5m by 3m, housing individual battery components with 2 no fitted external hvac systems for each unit and supported by 13 no. Inverter stations, 14 no. Auxiliary transformers and control container; (d) 220kv underground cable to the existing adjoining eirgrid substation; (e) associated elements comprising various underground cables and ducts, equipment plinths, boundary security fence, compound lighting and palisade gates and fencing, secuirty lighting, cctv, internal access roads, hardstanding areas and all necessary foundations works for the above compounds. The planning application is on lands where grid stabilisation facility was previously permitted under planning register no 19/115. Planning permission to construct the development is sought for a period of 10 years. A natura impact statment (nis) has been prepared in respect of the proposed development and accompanies the application
Key dates
Timeline
- Application received25 May 2021
- Decision due19 July 2021
- Decision issued19 July 2021
- Grant issued20 August 2021
- Permission expiry19 August 2026
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
THE DEVELOPMENT WILL CONSIST OF A GRID STABILISATION FACILITY COMPRISING OF: THE CONSTRUCTION UP TO 4 NO.…
KILPADDOGE , TARBERT , CO KERRY
19115KerryLodged 12 Feb 2019Energy
- Awaiting decisionAt this site
CONSTRUCT UP TO 4 NO. ROTATING STABILISERS, 5 NO. BATTERY STORAGE CONTAINERS, 1 NO. CONTROL ROOM, 2…
KILPADDOGE , TARBERT , CO KERRY
181290KerryLodged 21 Dec 2018Energy
- Granted50 m away
FOR CHANGES TO THE PREVIOUSLY PERMITTED PEAKER POWER PLANT DEVELOPMENT (PLANNING REF. 13/138). IT IS PROPOSED…
KILPADDOGE , TARBERT , CO KERRY
20850KerryLodged 18 Sept 2020Energy
- Granted250 m away
FOR A 10 YEAR PERMISSION TO CONSTRUCT A BATTERY ENERGY STORAGE SYSTEM (BESS) FACILITY ON A TOTAL SITE AREA OF…
KILPADDOGE , TARBERT , CO. KERRY
18878KerryLodged 10 Sept 2018Energy
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedEnergy
THE DEVELOPMENT WILL CONSIST OF A GRID STABILISATION FACILITY COMPRISING OF: THE CONSTRUCTION UP TO 4 NO.…
KILPADDOGE , TARBERT , CO KERRY
19115KerryLodged 12 Feb 2019
- GrantedEnergy
Development consisting of (a) A High Inertia Synchronous Compensator (HISC) compound containing 1 No. HISC…
Ballysumaghan , Sooey , County Sligo
22352SligoLodged 27 Oct 2022
- GrantedEnergy
AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A…
COOLCOR AND CLONIN , RHODE , CO. OFFALY
20238OffalyLodged 23 Jun 2020
- Awaiting decisionEnergy
PL2/20/238 FOR AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID…
COOLCOR AND CLONIN , RHODE , CO. OFFALY
EX26009OffalyLodged 27 May 2026
- GrantedInfrastructure
The development will consist of construction of a new 220kV gas insulated switchgear (GIS) Switchboard…
Poolbeg 220kV Electrical Substation and adjacent land, Pigeon House Road, Dublin 4 on site measuring 3.6haAB[ Ref:.
4057/23Dublin CityLodged 30 Jun 2023
- GrantedEnergy
A 10 YEAR PERMISSION FOR DEVELOPMENT WHICH CONSISTS OF THE CONSTRUCTION OF A SOLAR PV DEVELOPMENT WITH A…
RATHMOUNT MULLANAFAWNIA , AND RUSSELLSPENN , CO. OFFALY
20476OffalyLodged 5 Oct 2020
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.