Planning Permission Ireland
GrantedCommercialDecided 24 October 2019

Backweston Campus, Ballymadeer, Celbridge

Construction of a data hall building with external plant and backup generators at Backweston Campus.

19164 · Kildare County Council · Lodged 21 February 2019

Reference
19164
Authority
Kildare County Council
Register status
Decided
Type
PERMISSION
Received
21 February 2019

Summary

AI-generated

The development consists of a 5,474 sqm building with an additional 2,826 sqm external plant area. The facility includes data halls, offices, five backup generators, two substations, and a perimeter service road.

Commercialdata centregeneratorssubstation
Storeys
2
Floor area
5,474 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

The construction of 1 no. Building described as follows: the building is c. 5474sqm with an additional c. 2826sqm in external plant area and is made up of three distinct parts. The central two storey block has a mono-pitch roof structure, the ridge height of which is c. 15.15m and it accommodates the data halls and associated plant and equipment rooms. The front block has a flat roof structure with a parapet and is two storey with a parapet height of c. 10.60m and it accommodates the entrance reception, offices, meeting room, associated support areas, tea station, w. C. ’s, stores, plant areas including 5 no. Backup generators and 2 no. Substations (3mv). The third block is located to the rear of the main data hall block and consists mainly of an external two storey plant space with external stairways with intermediate level gangways. The two storey external plant area is screened (c. 10.6m) by a metal mesh structure. There are also two, two-storey flat roof internal plant rooms connecting to the central block. The provision of a perimeter service road/green road around the building to allow for access and maintenance of equipment to the front and rear of the block. The provision of a perimeter fence and access gates, hard and soft landscaping, signage and all associated site works. The area of the site relating to this planning application is 13,590sqm/1.359 hectares,

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
Blocks C D And E Hallwell Square, Tubber Lane, Adamstownprice excludes VATMar 2025€25,348,018233 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received21 February 2019
  2. Further information requested17 April 2019
  3. Further information received27 September 2019
  4. Decision due24 October 2019
  5. Decision issued24 October 2019
  6. Grant issued30 March 2020
  7. Appeal submitted20 November 2019
  8. Appeal decided11 March 2020
  9. Permission expiry29 March 2025

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.