Planning Permission Ireland
GrantedEnergyDecided 21 May 2024

Bigbog Coolnabacky Esker, Money Lower Loughteeog, Stradbally Co Laois

Amendments to a 110kV substation and solar array layout in Stradbally.

2460005 · Laois County Council · Lodged 3 January 2024

Reference
2460005
Authority
Laois County Council
Register status
Decided
Type
PERMISSION
Received
3 January 2024

Summary

AI-generated

Permission is sought to amend a previous planning permission to replace a permitted 110kV substation with an Air Insulation Switchgear substation, including a control building, palisade fencing, and realignment of solar arrays. The development also includes a new vehicular entrance, access track, and a 160m underground cable connection to the Coolnabacky substation.

Energysolarsubstationinfrastructureenergy
Storey
1
Floor area
134 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Amend planning permission reg. Ref. 17532 to consist of: replacement of permitted distribution network operator (dno) 110kv substation and all associated infrastructure (glass reinforced polyester (grp) cabinet, monitoring house, storage shed, auxiliary transformer and wc) with an air insulation switchgear (ais) 110kv substation comprising a single-storey control building (c. 6.28m height and c. 133.7sqm) within a palisade-fenced compound (c. 2.6m height and c. 1,779.8sq. M) and all associated electrical infrastructure and apparatus, and realignment of permitted solar arrays. The proposed development will consist of: construction of a new vehicular entrance and access track connecting to permitted internal vehicular tracks; construction of an underground cable (c. 160m length) to provide a tail fed connection to the permitted 400kv coolnabacky substation (an bord pleanála case ref. Pl11. Va0015); and, all ancillary site development works, including lighting, drainage, temporary construction compound and on-site parking to serve the operational and maintenance needs of the substation. A natura impact statement (nis) will be submitted to the planning authority with the application.

Key dates

Timeline

  1. Application received3 January 2024
  2. Further information requested27 February 2024
  3. Further information received27 March 2024
  4. Decision due21 May 2024
  5. Decision issued21 May 2024
  6. Appeal submitted17 June 2024
  7. Appeal decided8 January 2025
  8. Permission expiry7 January 2030

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.