Awaiting decisionEnergyDecision due today (23 July 2026)

Kilathmoy Substation, Athea Upper, Athea Co. Limerick

Development of a Long Duration Energy Storage facility at a substation.

2660215 · Limerick County Council · Lodged 27 February 2026

Reference
2660215
Authority
Limerick County Council
Register status
In progress
Type
PERMISSION
Received
27 February 2026

Summary

AI-generated

This application seeks a 10-year permission for a Long Duration Energy Storage facility containing a Battery Energy Storage System. The development includes removing existing grid support equipment and constructing BESS units, transformers, and associated infrastructure.

Energybattery storagesubstationrenewable energyinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Notice for renewable energy directive iii (red iii) development
  • 10 year permission for development of a long duration energy storage (ldes) facility at this site within the townland of athea upper, athea, co. Limerick. The development will consist of: (a) removal of selected items of existing grid support equipment and plant at the kilathmoy wind farm substation (2 no battery containers and associated inverters, transformers and hvac units, diesel generator and associated diesel tank, pre-fabricated electrical containers, sections of compound security fencing), and (b) construction of a long duration energy storage (ldes) facility containing a battery energy storage system (bess) compound consisting of bess units, (approximately 5m in height) with associated hvac units, transformers, inverters; underground cabling; 1 no pre-fabricated communications and control container; lighting, cctv, lightning masts; diesel generator and associated diesel tank; water storage tanks (approximately 3.6m in height); store containers; securing fencing, internal access track and access gates and all associated ancillary works including drainage, earthworks and retaining structures necessary to facilitate the development the application will replace the previously consented (but unbuilt) bess facility granted under planning ref (21/1702). A 10 year permission is being sought in respect of the development. A natura impact statement has been prepared as part of the application. This development is covered by the provisions of the renewable energy directive iii (directive (eu) 2023/2413) and it is important to note that the planning application may be subject to section 34d of the planning and development act, as amended. When a notice issues in accordance with section 34d(b), the provisions of article 26a of the planning and development regulations 2001 to 2025 shall apply

Key dates

Timeline

  1. Application received27 February 2026
  2. Further information requested2 June 2026
  3. Further information received26 June 2026
  4. Decision due23 July 2026

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.