BELLACORICK, BALLINA, CO. MAYO
Decommissioning, demolition, and a major substation extension in Bellacorick.
18274 · Mayo County Council · Lodged 23 April 2018
- Reference
- 18274
- Authority
- Mayo County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 23 April 2018
Summary
AI-generatedThe project involves decommissioning and removing electrical plant, demolishing a boundary fence, and extending the existing substation by 3,970 square metres. It will accommodate a 110kV conductor, a 16m high structure, a transformer, and associated electrical equipment.
- Floor area
- 3,970 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Decommissioning and removal of electrical plant and associated structures and the demolition of the existing fence along a portion of the north eastern boundary of the existing substation, the extension of the existing substation by 3970sq m to accommodate c. 30m of over head 110kv conductor connecting to an existing 110 kv busbar and associated structures c. 16m high, incorporating lightening protection measures, 1 no. 38/110kv bunded transformer, and additional 38 kv electrical equipment such as arc suppression coil, cable chairs/sealing ends, etc. All ancillary works within the site including the provision of additional areas of hard-standing, internal access-ways, associated drainage works and all works associated with removal, relocation, replacement and installation of underground cables, electrical plant and switchgear on the site, and a 2.6m high palisade perimeter fence with a dedicated access gate
Built & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Recent sales nearby
within 500 m| Address | Date | Price | Distance |
|---|---|---|---|
| Bellacorick, Ballina, Mayo | May 2026 | €144,000 | 197 m |
Nearby properties, not this site — a guide to local values.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received23 April 2018
- Decision due17 June 2018
- Decision issued12 June 2018
- Grant issued17 July 2018
- Permission expiry16 July 2023
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Granted50 m away
A c.3 MW CAPACITY BATTERY STORAGE FACILITY AND WILL — SUBJECT TO DETAILED DESIGN, COMMERICAL AND TECHNICAL…
BELLACORICK , BALLINA , CO. MAYO
18190MayoLodged 22 Mar 2018Energy
- Awaiting decision140 m away
Change of sue of former residential garda station to community center/tourist hostel. Construction of single…
Bellacorrick , Ballina
26112MayoLodged 21 May 2026Change of use
- Granted140 m away
Synchronous condenser/flywheel, located within a fenced compound of c.0.85 ha consisting of: machine building…
Shranakilla Road , Bellacorick , Co. Mayo
23162MayoLodged 24 Mar 2023Energy
- Granted290 m away
CONTINUE THE USE OF THE EXISTING 36 METRE HIGH, FREE STANDING LATTICE TYPE COMMUNICATIONS STRUCTURE, CARRYING…
BELLACORRICK , BALLINA
17419MayoLodged 31 May 2017Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionInfrastructure
The construction of a new 110/38kV/MV electrical substation and will include the following elements — Removal…
Roches Avenue , Raheen Business Park , Limerick.
25323893LimerickLodged 26 Nov 2025
- GrantedInfrastructure
Consists of works located within the existing substation and will comprise: (1) demolition of an existing…
Kinsale 38kV substation, Coolvallanane Beg, Kinsale, Co. Cork
196769corkLodged 20 Nov 2019
- GrantedInfrastructure
The development will consist of a physical extension of c. 300 sq.m to the existing electricity substation…
The existing ESB Athboy 38kV Substation , townlands of Martinstown , Athboy Co. Meath
2360497MeathLodged 20 Dec 2023
- GrantedInfrastructure
The development will consist of a physical extension of c. 1200 sq.m to the existing electricity substation…
ESB 110kV Substation , Mount Avenue Dundalk County Louth (Townland - Farrandreg) , OS map no. 1631-20 1631-25 1631-D 1701-05 AND 1701-B
2560674LouthLodged 22 Oct 2025
- GrantedInfrastructure
10 Year Planning Permission for a physical extension of c. 562 sq.m to the existing electricity substation…
The Existing Cloyne 38kV Substation, Demesne, Cloyne, Co Cork
255257corkLodged 27 Jun 2025
- GrantedInfrastructure
DEVELOP (A) SITE CLEARANCE WORKS INCLUDING REMOVAL OF EXISTING FENCING AND GATES , AND ELECTRICAL PLANT…
LISSYVIGGEEN , KILLARNEY , CO KERRY
19890KerryLodged 22 Aug 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.