AGHALUSKY, CASTLEBAR, CO. MAYO
Refurbishment works to a 57km long 110kV overhead electricity line between Castlebar and Cloon.
22780 · Mayo County Council · Lodged 8 September 2022
- Reference
- 22780
- Authority
- Mayo County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 8 September 2022
Summary
AI-generatedThe project involves refurbishment works to the existing Castlebar-Cloon 110kV overhead line, which spans approximately 57 kilometres. The line comprises 252 wooden polesets and 40 steel angle masts across counties Mayo and Galway.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
Works to refurbish the existing castlebar-cloon 110kv overhead line which is approximately 57km long, and comprises 252 no. Wooden polesets and 40 no. Steel angle masts between the existing castlebar 110kv substation in the townland of aghalusky, and the existing cloon 110kv substation in the townland of cloonascragh, co. Galway. Approximately 20km of the existing circuit is located within the functional area of galway county council and approximately 37km in the functional area of mayo county council
Built & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Recent sales nearby
within 500 m| Address | Date | Price | Distance |
|---|---|---|---|
| Farmhill, Claremorris, Cloonbonniff | Jul 2025 | €35,000 | 445 m |
Nearby properties, not this site — a guide to local values.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received8 September 2022
- Further information requested1 November 2022
- Further information received9 March 2023
- Decision due3 May 2023
- Decision issued17 April 2023
- Grant issued18 May 2023
- Permission expiry17 May 2028
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedInfrastructure
To refurbish the existing Castlebar-Cloon 110kV overhead line, which is approximately 57km long, and…
Cloonascragh ,
221030galwayLodged 7 Sept 2022
- GrantedInfrastructure
EirGrid PLC, with the consent and approval of the Electricity Supply Board (ESB), intends to apply for…
Existing Castlebar - Dalton 110kV overhead power line , See Particulars for multiple townlands , Co Mayo
2560928MayoLodged 15 Dec 2025
- GrantedInfrastructure
For works associated with the refurbishment of the existing Moneypoint — Oldstreet 400 kV overhead line…
Ballyhanry to Abbeyville ,
161747galwayLodged 22 Dec 2016
- GrantedInfrastructure
Permission for development which consists of; works to uprate the existing Cashla — Salthill 110kV overhead…
Existing Cashla-Salthill 110kV overhead line (OHL) , in the townlands of , Ballybaan Beg Parkmore and Castlegar
2560012Galway CityLodged 20 Jan 2025
- GrantedInfrastructure
For the development of this site, the existing Cloon to Lanesboro 110 KV Overhead line which is approximately…
Cloon Substation south of Tuam to Creggs Village ,
18896galwayLodged 28 Jun 2018
- GrantedInfrastructure
FOR THE DEVELOPMENT ASSOCIATED WITH THE UPRATE OF A SECTION OF THE EXISTING CLASHAVOON TO TARBERT 220KV…
SHRONEBEIRNEDOONEEN , GLANLAREHAN AND , KNOCKNABOUL
161284KerryLodged 22 Dec 2016
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.