C. 5.14 HA SITE WITHIN THE MOUNT LUCAS WIND FARM, IN THE TOWNLAND OF DRUMCAW OR MOUNTLUCAS, CO.OFFALY
A 2MW pilot-scale hydrogen electrolysis plant is proposed within the Mount Lucas Wind Farm.
22353 · Offaly County Council · Lodged 15 July 2022
- Reference
- 22353
- Authority
- Offaly County Council
- Register status
- Invalid or incomplete
- Type
- PERMISSION
- Received
- 15 July 2022
Summary
AI-generatedThe development will feature an electrolyser in a container, high-pressure hydrogen storage units, a compression system, and a medium voltage underground cable connection to a nearby wind turbine. Supporting infrastructure includes buffer tanks, borehole wells, HGV trailer bays, and security fencing.
- Floor area
- 24 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A 2mw pilot scale hydrogen electrolysis plant which comprises; an electrolyser contained within a standard iso container (c. 12.2m in length, c. 2.4m in width and c. 3.3m in height), 3 no. High pressure hydrogen storage units, 1 no hydrogen compression system, 1 no generator, 2 no substation / transformer structures and a medium voltage underground cable connection to the nearest wind turbine c. 600m to the west. The hydrogen electrolysis plant will be supported by the following infrastructure; hydrogen analyser container, firewall (maximum height 3.6m), underground fibre optic cabling, 2 no. 10 cubic metre buffer tanks, gas control cabinet, power supply unit, 23 cubic metre precast underground water storage tank, water filtration system, 2 no borehole wells, and 4 no. Hgv trailer bays. Ancillary infrastructure will include 1 no welfare portacabin (c. 24sqm) and 4 no. Car spaces, palisade security fencing, vehicular and pedestrian access, a replacement footpath between the site entrance and the main entrance to the wind farm, site drainage works including petrol interceptor and all associated infrastructure and site development works. The application is accompanied by a natura impact statement (nis)
Key dates
Timeline
- Application received15 July 2022
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- GrantedAt this site
A 2MW PILOT SCALE HYDROGEN ELECTROLYSIS PLANT WHICH COMPRISES; AN ELECTROLYSER CONTAINED WITHIN A STANDARD…
C.5.14HA SITE WITHIN THE MOUNT LUCAS WIND FARM , IN THE TOWNLAND OF DRUMCAW OR , MOUNTLUCAS CO. OFFALY
22379OffalyLodged 29 Jul 2022Energy
- Granted300 m away
CONSTRUCTION OF A NEW TRAINING BUILDING COMPRISING OF A SINGLE-STOREY TRAINING WORKSHOP AND A TWO STOREY…
THE NATIONAL CONSTRUCTION TRAINING CENTRE DRUMCAW , OR MOUNTLUCAS/DERRYCRICKET , DAINGEAN CO. OFFALY R35 XW10
18411OffalyLodged 27 Sept 2018Commercial
- Awaiting decision340 m away
21347 FOR EXTENSION TO EXISTING SLATTED CATTLE HOUSE TO INCLUDE UNDERGROUND SLATTED SLURRY STORAGE, DRY…
ENDRIM , FERBANE , CO. OFFALY
EX26010OffalyLodged 8 Jun 2026Agricultural
- Awaiting decision340 m away
The construction of a new MMC Training Building comprising of a single-storey training workshop, a two storey…
National Construction Training Campus , Drumcraw or Mountlucas Daingean , Co. Offaly
2660307OffalyLodged 5 Jun 2026Commercial
- Granted400 m away
(A) The construction of Phase 1 of the Modern Methods of Construction (MMC) Demonstration Park consisting of…
National Construction Training Centre , Drumcraw or Mountlucas / Derrycricket , Daingean Co. Offaly
2360183OffalyLodged 13 Nov 2023Infrastructure
- Awaiting decision400 m away
(A) The construction of Phase 1 of the Modern Methods of Construction (MMC) Demonstration Park consisting of…
National Construction Training Centre , Drumcraw or Mountlucas / Derrycricket , Daingean Co. Offaly
2360155OffalyLodged 23 Oct 2023Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedEnergy
A 2MW PILOT SCALE HYDROGEN ELECTROLYSIS PLANT WHICH COMPRISES; AN ELECTROLYSER CONTAINED WITHIN A STANDARD…
C.5.14HA SITE WITHIN THE MOUNT LUCAS WIND FARM , IN THE TOWNLAND OF DRUMCAW OR , MOUNTLUCAS CO. OFFALY
22379OffalyLodged 29 Jul 2022
- GrantedEnergy
The proposed development consists of the construction of a hydrogen production facility comprising a hydrogen…
0.56 hectares site within ESB Aghada Generating, Station Ballincarroonig, Aghada, Co Cork P25 XE94
244026corkLodged 10 Jan 2024
- GrantedEnergy
DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE…
COOLCOR , RHODE , CO OFFALY
20237OffalyLodged 23 Jun 2020
- GrantedEnergy
(1) REMOVAL OF THE EXISTING 8 NO. 600 AND 660 KILOWATT (KW) TURBINES AND REPLACEMENT WITH 3 NO. 4.5 MEGAWATT…
MEENDERRYGAMPH , GWEEDORE , CO. DONEGAL
2250813DonegalLodged 11 May 2022
- RefusedEnergy
A TEN YEAR PLANNING PERMISSION FOR A WIND FARM WITH A 30 YEAR OPERATIONAL LIFE (FROM THE DATE OF…
MOMEEN & LETTERGULL , CO. DONEGAL
1850156DonegalLodged 7 Feb 2018
- Awaiting decisionEnergy
The proposed development will comprise a 208MW (electrical output) Open Cycle Gas Turbine (OCGT) Power Plant…
Carranstown & Caulstown , Platin , Duleek Co. Meath
LB181494MeathLodged 13 Dec 2018
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.