GrantedEnergyDecided 14 April 2023

MEENDERRYGAMPH, GWEEDORE, CO. DONEGAL

Decommissioning of 8 wind turbines and replacement with 3 larger 4.5MW turbines in Gweedore.

2250813 · Donegal County Council · Lodged 11 May 2022

Reference
2250813
Authority
Donegal County Council
Register status
Decided
Type
PERMISSION
Received
11 May 2022

Summary

AI-generated

The project involves removing 8 existing wind turbines and replacing them with 3 new 4.5MW turbines up to 150m in height. It includes a new 38kV substation, a borrow pit, and associated access tracks, with a 10-year permission and 40-year operational life.

Energywind energysubstationeiarinfrastructure

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

(1) removal of the existing 8 no. 600 and 660 kilowatt (kw) turbines and replacement with 3 no. 4.5 megawatt turbines having an overall maximum height of 150m consisting of a blade diameter of 136m and a hub height of 82m. The development will also consist of the associated turbine hardstands and foundations, upgrading of c. 910m of existing site access track, provision of c. 799m of new site access track, construction of a new 38kv substation and 2 no. Joint bays, development of a new borrow pit, temporary construction compound, site drainage network, the removal and restoration of c. 600m of existing site track, internal wind farm underground power and communications cabling, connection to the national electricity network by joining to existing grid connections prior to leaving the site and all associated site development and ancillary works. This application is seeking a ten year permission and a 40 year operational life from the date of commissioning of the wind farm. This application is accompanied by an environmental impact accessment report (eiar) & a natura impact statement (nis)

Key dates

Timeline

  1. Application received11 May 2022
  2. Further information requested30 June 2022
  3. Further information received22 February 2023
  4. Decision due18 April 2023
  5. Decision issued14 April 2023
  6. Grant issued17 May 2023
  7. Permission expiry16 May 3033

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.