C.5.14HA SITE WITHIN THE MOUNT LUCAS WIND FARM, IN THE TOWNLAND OF DRUMCAW OR, MOUNTLUCAS CO. OFFALY
Construction of a 2MW pilot-scale hydrogen electrolysis plant within Mount Lucas Wind Farm.
22379 · Offaly County Council · Lodged 29 July 2022
- Reference
- 22379
- Authority
- Offaly County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 29 July 2022
Summary
AI-generatedThe development comprises an electrolyser in a container, three high-pressure hydrogen storage units, a compression system, and a medium-voltage underground cable connection to a nearby wind turbine. It includes supporting infrastructure such as buffer tanks, borehole wells, and HGV trailer bays.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A 2mw pilot scale hydrogen electrolysis plant which comprises; an electrolyser contained within a standard iso container (c. 12.2m in length, c. 2.4m in width and c. 3.3m in height), 3 no. High pressure hydrogen storage units, 1 no hydrogen compression system, 1 no generator, 2 no substation/transformer structures and a medium voltage underground cable connection to the nearest wind turbine c. 600m to the west. The hydrogen electrolysis plant will be supported by the following infrastructure; hydrogen analyser container, firewall (maximum height 3.6m), underground fibre optic cabling, 2 no. 10 cubic metre buffer tanks, gas control cabinet, power supply unit, 23 cubic metre precast underground water storage tank, water filtration system, 2 no borehole wells, and 4 no. Hgv trailer bays. Ancillary infrastructure will include 1 no welfare portacabin (c. 24sqm) and 4 no. Car spaces, palisade security fencing, vehicular and pedestrian access, a replacement footpath between the site entrance and the main entrance to the wind farm, site drainage works including petrol interceptor and all associated infrastructure and site development works. The application is accompanied by a natura impact statement (nis)
Key dates
Timeline
- Application received29 July 2022
- Further information requested22 September 2022
- Further information received1 February 2023
- Decision due28 March 2023
- Decision issued28 March 2023
- Grant issued4 May 2023
- Permission expiry3 May 2028
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decisionAt this site
A 2MW PILOT SCALE HYDROGEN ELECTROLYSIS PLANT WHICH COMPRISES; AN ELECTROLYSER CONTAINED WITHIN A STANDARD…
C. 5.14 HA SITE WITHIN THE MOUNT LUCAS WIND FARM , IN THE TOWNLAND OF DRUMCAW OR MOUNTLUCAS , CO.OFFALY
22353OffalyLodged 15 Jul 2022Energy
- Granted300 m away
CONSTRUCTION OF A NEW TRAINING BUILDING COMPRISING OF A SINGLE-STOREY TRAINING WORKSHOP AND A TWO STOREY…
THE NATIONAL CONSTRUCTION TRAINING CENTRE DRUMCAW , OR MOUNTLUCAS/DERRYCRICKET , DAINGEAN CO. OFFALY R35 XW10
18411OffalyLodged 27 Sept 2018Commercial
- Awaiting decision330 m away
21347 FOR EXTENSION TO EXISTING SLATTED CATTLE HOUSE TO INCLUDE UNDERGROUND SLATTED SLURRY STORAGE, DRY…
ENDRIM , FERBANE , CO. OFFALY
EX26010OffalyLodged 8 Jun 2026Agricultural
- Awaiting decision330 m away
The construction of a new MMC Training Building comprising of a single-storey training workshop, a two storey…
National Construction Training Campus , Drumcraw or Mountlucas Daingean , Co. Offaly
2660307OffalyLodged 5 Jun 2026Commercial
- Granted400 m away
(A) The construction of Phase 1 of the Modern Methods of Construction (MMC) Demonstration Park consisting of…
National Construction Training Centre , Drumcraw or Mountlucas / Derrycricket , Daingean Co. Offaly
2360183OffalyLodged 13 Nov 2023Infrastructure
- Awaiting decision400 m away
(A) The construction of Phase 1 of the Modern Methods of Construction (MMC) Demonstration Park consisting of…
National Construction Training Centre , Drumcraw or Mountlucas / Derrycricket , Daingean Co. Offaly
2360155OffalyLodged 23 Oct 2023Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
A 2MW PILOT SCALE HYDROGEN ELECTROLYSIS PLANT WHICH COMPRISES; AN ELECTROLYSER CONTAINED WITHIN A STANDARD…
C. 5.14 HA SITE WITHIN THE MOUNT LUCAS WIND FARM , IN THE TOWNLAND OF DRUMCAW OR MOUNTLUCAS , CO.OFFALY
22353OffalyLodged 15 Jul 2022
- GrantedEnergy
The proposed development consists of the construction of a hydrogen production facility comprising a hydrogen…
0.56 hectares site within ESB Aghada Generating, Station Ballincarroonig, Aghada, Co Cork P25 XE94
244026corkLodged 10 Jan 2024
- GrantedEnergy
DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE…
COOLCOR , RHODE , CO OFFALY
20237OffalyLodged 23 Jun 2020
- GrantedEnergy
(1) REMOVAL OF THE EXISTING 8 NO. 600 AND 660 KILOWATT (KW) TURBINES AND REPLACEMENT WITH 3 NO. 4.5 MEGAWATT…
MEENDERRYGAMPH , GWEEDORE , CO. DONEGAL
2250813DonegalLodged 11 May 2022
- RefusedEnergy
A TEN YEAR PLANNING PERMISSION FOR A WIND FARM WITH A 30 YEAR OPERATIONAL LIFE (FROM THE DATE OF…
MOMEEN & LETTERGULL , CO. DONEGAL
1850156DonegalLodged 7 Feb 2018
- RefusedEnergy
A TEN YEAR PLANNING PERMISSION FOR A RENEWABLE ENERGY DEVELOPMENT WITH A 40-YEAR OPERATIONAL LIFE FROM THE…
MASSLOUGHDERRYDUFF LACKAGHATERMON , ARDARA , DONEGAL PO
2251393DonegalLodged 19 Aug 2022
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.