Planning Permission Ireland
Awaiting decisionEnergyDecision due in ~4 weeks (20 August 2026)

Pollymount Bellanamullia Scramoge, Treanaceeve and Ballyhubert, County Roscommon.

Construction of a six-turbine wind farm and associated substation in County Roscommon.

2560446 · Roscommon County Council · Lodged 15 September 2025

Reference
2560446
Authority
Roscommon County Council
Register status
In progress
Type
PERMISSION
Received
15 September 2025

Summary

AI-generated

The project consists of six wind turbines with a maximum tip height of up to 160m. It also includes turbine foundations, hardstands, 4.4km of access tracks, and a permanent 38kV electrical substation.

Energywind farmrenewablesubstationenergy
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • Permission for development consisting of
  • The construction and operation of a wind farm consisting of six wind turbines
  • The turbine specification is unconfirmed but will fall within the parameter range outlined by roscommon county council and will be one of the following three options; - technology option
  • Tip height of 160m, rotor diameter of 136m and hub height of 92m; or - technology option
  • Tip height of 156m, rotor diameter of 133m and hub height of 90m; or - technology option
  • Tip height of 159m, rotor diameter of 138m and hub height of 90m
  • Construction of turbine hardstands (including crane and assembly areas) and turbine foundations
  • Construction of approximately 3.9km of new permanent internal site access tracks and the upgrade of 0.5km of existing internal site access tracks
  • Construction of a permanent onsite 38kv electrical substation, including one single storey substation building with welfare facilities, lidar, diesel generator and fuel storage tank, all associated electrical plant and equipment, all associated underground cabling, rainwater harvesting and storage tank, wastewater holding tank, security fencing, gates, signage, and all ancillary structures and works
  • Installation of underground electrical and communications cabling connecting the wind turbines to the proposed onsite 38kv electrical substation
  • Construction of two temporary site compounds with associated site offices, welfare facilities, car parking, site fencing and lighting
  • Erection of a permanent 30m high communications relay tower
  • Construction access via six site entrances (se1 – se6) to include: - se1 on the r371, se2 and se3 on the l6018, and se4, se5 and se6 on the l60498; - se1 and se6 are temporary and will be reinstated following construction. Se1 may be re-established if required for turbine component repair or replacement. Se2 – se5 will be retained permanently for operational access
  • Tree felling to facilitate the construction and operation of the proposed development
  • Installation of approximately 5.1km of permanent underground electrical cabling for the grid connection including cabling within the public road corridor, extending from the proposed onsite 38kv electrical substation at ballyfeeny to end at the junction of the r371 and the sliabh bawn substation road in the townland of tooreen
  • All associated site works, including site clearance, landscaping, site drainage, s

Key dates

Timeline

  1. Application received15 September 2025
  2. Further information requested23 December 2025
  3. Further information received5 June 2026
  4. Decision due20 August 2026

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.