GrantedIndustrialDecided 13 February 2025

MSD Ireland (Ballydine), Ballydine, Kilsheelan Clonmel Co. Tipperary

A four-storey extension to an existing pharmaceutical factory building.

2460825 · Tipperary County Council · Lodged 27 September 2024

Reference
2460825
Authority
Tipperary County Council
Register status
Decided
Type
PERMISSION
Received
27 September 2024

Summary

AI-generated

Permission is sought for a new 4-level extension to the southern elevation of the existing factory 03 building at the MSD Ireland facility in Ballydine. The development will provide approximately 2,967 sqm of gross floor area with a maximum height of 29.11m on a site operating under an Industrial Emissions Licence.

Industrialfactoryindustrialextension
Storeys
4
Floor area
2,967 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

An extension to the existing factory 03 production building at the site at ballydine, kilsheelan, clonmel, co. Tipperary. The development will consist of: (i) a new 4 level extension to the southern elevation of the existing factory 03 building to provide a gross floor area of approximately 2,967 sqm and maximum height to parapet of 29.11m; (ii) all associated site development and ancillary works including modifications to internal roads, footpaths, underground drainage and utility services, provision of low level (height c. 0.5 m) retaining wall, adjustment of the existing high level piperacks/cable trays for connections into the proposed building and landscaping works. The proposed development is located on a site that operates under an existing industrial emissions (ie) licence under part iv of the environmental protection agency act 1992 (as amended for the protection of the environment act, 2003). The proposed development is on a site which the chemicals act (control of major accident hazards involving dangerous substances) regulations 2015 applies

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Built — construction complete

A commencement notice records works starting on 3 April 2025.

Notified floor area: 2,781.7

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received27 September 2024
  2. Further information requested20 November 2024
  3. Further information received13 December 2024
  4. Decision due15 February 2025
  5. Decision issued13 February 2025
  6. Grant issued19 March 2025
  7. Permission expiry18 March 2030

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.