GrantedEnergyDecided 29 September 2021

Ballygeery West, Co Clare

A 10-year permission is sought for a synchronous condenser grid-stabilising facility in Ballygeery West.

21497 · Clare County Council · Lodged 20 May 2021

Reference
21497
Authority
Clare County Council
Register status
Decided
Type
PERMISSION
Received
20 May 2021

Summary

AI-generated

The development on a 1-hectare site behind the existing ESB substation will consist of a 250 to 500 MVA synchronous condenser to stabilise the electricity grid. It includes a 540 square metre compound building, cooling equipment, modular control containers, a transformer, and underground cabling.

Energygrid stabilityinfrastructuresubstation
Floor area
895 m²

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

To apply for a 10 year planning permission for development on a c. 1 ha at ballygeery west, co clare. The development will consist of the development and operation of a 250 to 500 mva (electrical rating) synchronous condenser. The development which will be located within a site compound of c. 1 hectare behind the existing esb substation for the purpose of stabilising the electricity grid will consist of the following elements; compound building, within which the synchronous condenser generator and flywheel will be located (540m2c. 7m high), synchronous condenser, with a 250-500 mva (electrical rating); cooling equipment (c. 160sqm. , c. 3m high); 6 no. Modular containers to house electrical and control equipment (total area of c. 195sqm. , c. 5m high), a generator step-up transformer, auxiliary transformer and electrical plant including an external circuit breaker (c. 8m high); 1 no. Firefighting water tank and pump, an above-ground oil separator and collection pit, boundary fencing (c. 3m high), palisade security entrance gate and cctv, c. 100m of underground cabling ducts and cable to the neighbouring esb substation, all other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of area of hard standing including a maintenance lay-down area. Planning permission is being sought for a duration of 10 years

Key dates

Timeline

  1. Application received20 May 2021
  2. Further information requested8 July 2021
  3. Further information received6 September 2021
  4. Decision due3 October 2021
  5. Decision issued29 September 2021
  6. Grant issued3 November 2021
  7. Permission expiry2 November 2031

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.