Former Calor Site, Breakwater Road North, Dublin Port, Dublin 1
Site works and security upgrades at a SEVESO port site, including new fencing, lighting, and gates.
3269/18 · Dublin City Council · Lodged 15 June 2018
- Reference
- 3269/18
- Authority
- Dublin City Council
- Register status
- Decided
- Type
- Permission
- Received
- 15 June 2018
Summary
AI-generatedThe development at Dublin Port consists of removing plinths and vegetation, constructing new pavement, and installing drainage and electrical infrastructure. It also includes 18m CCTV poles, high lighting columns, security fencing, a fire wall, and a 12m wide sliding gate.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
The development will consist of: the removal of plinths, fences and vegetation etc; new pavement construction including underground drainage and electricity infrastructure; 2 no. Cctv poles (18m high); new lighting (including 2 no. Lighting columns 30m high and 10 no. Lighting columns 12m high); new 4m high security fence on western and southern boundaries; new 7.2m high fire wall on the eastern boundary and; a 5m sliding gate as fire access on the south eastern corner of the site. The development will also include the closure of the existing site accesses and modifications to the proposed access permitted under reg. Ref. 3084/16, to provide a 12m wide sliding gate on breakwater road north. All development to take place on a site approx. 0.3 hectares. The application is for a 10 year planning permission. The site of the proposed development is a seveso site.
Land-use zoning
What this land is zoned for
“To provide for the protection and creation of industrial uses, and facilitate opportunities for employment creation including Port Related Activities.”
National zoning type: General industry
Objective set by the Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planKey dates
Timeline
- Application received15 June 2018
- Further information requested9 August 2018
- Further information received31 August 2018
- Decision due27 September 2018
- Decision issued27 September 2018
- Grant issued6 November 2018
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Granted150 m away
The construction of a vehicle service/maintenance facility and office accommodation contained in one building…
Calor, Tolka Quay Road, Dublin Port, Dublin 1
3143/18Dublin CityLodged 30 May 2018Commercial
- Granted160 m away
The development will consist of: The construction of a 3 bay maintenance facility comprising of 2 no. single…
Calor, Tolka Quay Road, Dublin 1
4574/19Dublin CityLodged 28 Nov 2019Commercial
- Granted170 m away
Permission for development at the former Asahi Site, Breakwater Road North, Dublin Port, Dublin — The…
Asahi Site, Breakwater Road North, Dublin Port, Dublin 1
3488/18Dublin CityLodged 12 Jul 2018Infrastructure
- Granted230 m away
Planning Permission for development at this site address: Circle K Yard 3, Alexandra Road, Dublin Port,…
Circle K, Yard 3, Alexandra Road, Dublin Port, Dublin 1
2071/20Dublin CityLodged 20 Jan 2020Industrial
- Granted240 m away
Modifications to existing workshop, ancillary office and welfare facilities to provide additional…
Dublin Ferryport Terminals (DFT), Breakwater Road North, Dublin 1, D01 V3H3
WEB5107/25Dublin CityLodged 10 Sept 2025Industrial
- Granted270 m away
Demolition of a single storey office building (785sq.m); demolition of a maintenance shed building…
Calor Office Site, Tolka Quay Road,Dublin Port, Dublin 1
3540/18Dublin CityLodged 20 Jul 2018Demolition
- Granted320 m away
The development will consist of; the demolition of existing ESB Substation (approx. 25sq.m and 3.2m heigh),…
Tolka Quay Road, Dublin Port, Dublin 1
4250/18Dublin CityLodged 24 Oct 2018Infrastructure
- Granted330 m away
Planning permission for development at the following adjacent sites: Top Oil Yard 1, Promenade Road, Parish…
Top Oil Yard 1, Promenade Road, Parish of Saint Thomas, Dublin Port, Dublin 3, D03 HK83
3671/21Dublin CityLodged 11 Oct 2021Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedCommercial
The construction of a vehicle service/maintenance facility and office accommodation contained in one building…
Calor, Tolka Quay Road, Dublin Port, Dublin 1
3143/18Dublin CityLodged 30 May 2018
- GrantedCommercial
The development will consist of: The construction of a 3 bay maintenance facility comprising of 2 no. single…
Calor, Tolka Quay Road, Dublin 1
4574/19Dublin CityLodged 28 Nov 2019
- GrantedInfrastructure
The proposed development will consist of the demolition of 10 no. redundant buildings (c. 6830sqm) and…
Terminal 4 North Lands, Dublin Port, Dublin 1, bounded by Bond Road, Tolka Quay Road & Promenade Road
4483/19Dublin CityLodged 18 Nov 2019
- GrantedChange of use
The development will consist of: (1) Permission for works comprising of: (i) Partial change of use from…
Former Agnelli Motors, Greenhills Road, Tallaght, Dublin, D24 PW77
SD25A/0129WSouth DublinLodged 8 Sept 2025
- InvalidInfrastructure
The development will consist of: a c.189m long, c.10m wide approach way and ramp; 1 no. office and staff…
Berth 49, Terminal 1, Dublin Port, Dublin 1
2756/19Dublin CityLodged 15 Apr 2019
- GrantedAlterations
The development consists of the amendment of previous permission Reg. Ref. 4658/18, as amended by Reg. Ref.…
20 Merrion Road, Ballsbridge, Dublin 4
3027/20Dublin CityLodged 15 Jul 2020
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.