Kilshane Road, Kilshane, Finglas, Dublin 11.
Construction of a new 293 Megawatt gas turbine power generation station and associated road realignment works.
FW22A/0204 · Fingal County Council · Lodged 3 May 2023
- Reference
- FW22A/0204
- Authority
- Fingal County Council
- Register status
- Decided
- Type
- Permission
- Received
- 3 May 2023
Summary
AI-generatedThe development consists of a new gas turbine power station with a 28m high exhaust stack, admin building, warehouse, and fuel/water tanks. It also requires the demolition of an existing house and farm buildings, alongside significant road realignment and improvements to Kilshane Road.
- Floor area
- 1,440 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- The proposed development will consist of the following
- The construction of a new gas turbine power generation station with an output of up to 293 megawatts. The proposed station will consist of 1 no. Gas turbine and 1 no. 28 m high exhaust stack partially enclosed by a 12 m high acoustic wall. 1 no. Single storey admin building and warehouse (c. 926 m2), 1 no. Single storey packaged electronic/electrical control compartment (peecc) (c. 72 m2), 1 no. Single storey continuous emission monitoring system (cems) shelter (c. 14.8 m2), 1 no. 16.2m high x 024.4m fuel oil tank, 1 no. 15.3m high x 09.2m raw/fire water tank, 1 no. 16.2m high x 018.3m demin water tank, and miscellaneous plant equipment
- The demolition of a detached residential dwelling (c. 142 m2 gfa) and associated farm buildings (c. 427 m2 gfa) located in the north west corner of the subject site to facilitate the proposed development
- Road improvement works to 493.34 m kilshane road (l3120), including the realignment of a portion of the road (293.86 m) within the subject site boundary and the provision of new footpaths, off-road cycle ways, together with the construction of a new roundabout linking the proposed realignment of kilshane road back to the existing road network to the northeast of the subject site and to the proposed internal road network to serve the proposed development
- The construction of entrance gates, low wall and railings fronting the realigned kilshane road and a private internal road network providing for vehicular, cyclist and pedestrian access to serve the development. Construction of 3 m high security fencing within development. S. Total provision of 26 no. Car parking spaces including 1 no. Disabled persons parking space and 2 no. Ev electrical charging points
- Provision of security lighting columns to serve the development and the installation of closed-circuit television system (cctv) for surveillance and security purposes
- Provision of 20 no. Sheltered bicycle parking spaces
- Provision of hard and soft landscaping works, tree planting and boundary treatments including 3 m high security fence along kilshane road and the perimeter of the subject site boundary
- Provision of new on-site foul sewer pumping station to serve the development
- Provision of underground surface water attenuation areas to serve the development. All associated site development and excavation works, above and below ground, necessary to facilitate the development. An environmental impact assessment report has been prepared in respect of the proposed development. This application relates to a development that will require an industrial emissions directive licence from the environmental protection agency. A subsequent application will be submitted for an above ground installation (agi) compound, underground gas supply installation and a subsequent strategic infrastructure development (sid) application will also be submitted for a gas-insulated switchgear substation (gis), air insulated switchgear substation (ais) and grid connection to serve the development. Ai received 11/01/23 sai received 18/01/23 cai recieved 24/04/2023 sai received 03/05/23
Land-use zoning
What this land is zoned for
“Provide for heavy industry”
National zoning type: General industry
Objective set by the The Fingal Development Plan 2023 – 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planKey dates
Timeline
- Application received3 May 2023
- Decision due26 June 2023
- Decision issued23 June 2023
- Appeal submitted30 June 2023
- Appeal decided16 May 2024
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Refused30 m away
Planning permission is being sought for a development that will consis
Kilshane Road, Kilshane, Finglas, Dublin 11.
FW21A/0250FingalLodged 16 Dec 2021Other
- Invalid30 m away
1. The construction of a Gas Turbine Power Generation Station with an
Kilshane Road, Kilshane, Finglas, Dublin 11.
FW21A/0230FingalLodged 26 Nov 2021Energy
- Invalid60 m away
The proposed development will consist of 1No. Electrical & Instrumentation Kiosk (24 sqm), 1 No. Packaged…
Kilshane Road, Kilshane, Finglas, Dublin 11
FW25A/0502EFingalLodged 19 Nov 2025Infrastructure
- Granted80 m away
The proposed development will consist of 1No. Electrical & Instrumentation Kiosk (24 sqm), 1 No. Packaged…
Kilshane Road, Kilshane, Finglas, Dublin 11
FW25A/0516EFingalLodged 1 Dec 2025Infrastructure
- Granted120 m away
Kilshane Energy Ltd. intends to apply for planning permission for revisions to previously approved Gas…
Kilshane Road, Kilshane, Finglas, Dublin 11
FW25A/0523EFingalLodged 28 Nov 2025Energy
- Refused280 m away
The proposed development consists of the following: The demolition of existing dwellings (Bloomburn Cottage,…
Bloomburn Cottage, Kilshane, Dublin 11, D11 F1WB., and Kilmonan Lodge, Kilshane, Dublin 11, D11XP89.
FW24A/0045FingalLodged 9 Feb 2024Commercial
- Withdrawn290 m away
Pam Energy Supplies Limited, intend to apply to the aforementioned Planning Authority for permission for…
Lands at Kilshane Road, Kilshane, Finglas, Dublin 11
FW23A/0232FingalLodged 8 Aug 2023Energy
- Refused330 m away
The proposed development consists of the following: The demolition of two no. existing detached dwellings…
Bloomburn Cottage, Kilshane, Dublin 11, D11 F1WB., and Kilmonan Lodge, Kilshane, Dublin 11, D11XP89.
FW24A/0339EFingalLodged 20 Aug 2024Industrial
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- Awaiting decisionEnergy
In accordance with Section 37E of the Planning and Development Act 2000 (as amended) Kilshane Energy Ltd,…
Kilshane, Finglas, Dublin 11
SID/06/24FingalLodged 4 Oct 2024
- GrantedEnergy
Alterations to the development permitted under Reg. Ref.: SD18A/0068, as previously amended under Reg. Ref.:…
3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22
SD23A/0158South DublinLodged 12 Jul 2023
- GrantedEnergy
Kilshane Energy Ltd. intends to apply for planning permission for revisions to previously approved Gas…
Kilshane Road, Kilshane, Finglas, Dublin 11
FW25A/0523EFingalLodged 28 Nov 2025
- Awaiting decisionEnergy
The proposed development will comprise the following: Construction/ installation of an Open Cycle Gas Turbine…
Huntstown Power Station, Townlands of Kilshane, Huntstown and Johnstown, Dublin, D11 N406
FW26A/0163EFingalLodged 22 Apr 2026
- GrantedEnergy
The development comprises 275MWe reserve gas-fired generator to boost and back up the power system and will…
Kiltotan and Collinstown and Oldtown , Rochfortbridge , Co Westmeath
21515WestmeathLodged 21 Sept 2021
- Awaiting decisionEnergy
The proposed development will comprise a 208MW (electrical output) Open Cycle Gas Turbine (OCGT) Power Plant…
Carranstown & Caulstown , Platin , Duleek Co. Meath
LB181494MeathLodged 13 Dec 2018
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.