Windgates, Co. Kildare.
Construction of a Synchronous Compensator grid stabilisation facility in Kildare.
211444 · Kildare County Council · Lodged 7 October 2021
- Reference
- 211444
- Authority
- Kildare County Council
- Register status
- Decided
- Type
- PERMISSION
- Received
- 7 October 2021
Summary
AI-generatedThe development on a 1.97-hectare site includes a High Inertia Synchronous Compensator building, an electrical container area, external coolers, transformers, and a Gas Insulated Switchgear compound with an underground grid connection.
- Storey
- 1
- Floor area
- 481 m²
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
A synchronous compensator (electricity grid stabilisation) development within the townland of windgates, co. Kildare within a site area of approximately 1.97 hectares. Permission is sought for 1 high intertia synchronous compensator (hisc) compound (0.25 hectares) consisting of 1 no. High intertia synchronous compensator (hisc) building enclosed within a steel clad framed, housed structure (12.1m max height and 481 m2) and supported by an electrical container area measuring 355m2 consisting of 8 no. Electrical equipment containers with a total area of (238m2), each container measuring 29.75m2, and an external cooler area measuring 180m2 consisting of 4 no. External cooler units, each one measuring 30.5m2, 1 auxiliary and start up static frequency converter sfc transformer, 1 generator circuit breaker, 1 emergency diesel generator and 1 associated diesel storage tank; a high voltage (hv) compound (0.11 hectares) consisting of main transformer and high voltage (hv) equipment; a gas insulated switchgear (gis) building compound and underground grid connection (0.25 hectares) consisting of 1 high voltage gas insulated switchgear compound (0.16 hectares), included within this compound is a hv gas insulated switchgear (gis) housed structure (13.5m max height and 458m2) and 220kv underground cable connection (188m in length) to adjacent (existing) 220kv eirgrid substation; upgrade to the existing site entrance onto the r406, internal access tracks, fencing, temporary construction compound, landscaping and drainage. Planning permission is sought for a period of 10 years. A natura impact statement (nis) accompanies this application. All within the townland of
Key dates
Timeline
- Application received7 October 2021
- Further information requested29 November 2021
- Further information received21 April 2022
- Decision due18 May 2022
- Decision issued18 May 2022
- Grant issued5 October 2023
- Appeal submitted9 June 2022
- Appeal decided5 October 2023
- Permission expiry4 October 2028
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Awaiting decision180 m away
For construction of infrastructure, and associated development, at the existing and planned expanded…
Maynooth 220kV Substation , Taghadoe , Co. Kildare
2460400KildareLodged 2 May 2024Infrastructure
- Granted290 m away
For construction of a new 220 kV Gas Insulated Switchgear (GIS) building (83.5m long x 18.5m wide (25.1m…
Maynooth 220kV Substation , Taghadoe and Windgates , Co. Kildare
2460494KildareLodged 30 May 2024Infrastructure
- Awaiting decision300 m away
With the consent and approval of the Electricity Supply Board (ESB), for the construction of a new 220 kV Gas…
Maynooth 220kV Substation , Taghadoe , Co. Kildare
2360474KildareLodged 12 Dec 2023Infrastructure
- Awaiting decision320 m away
For the construction of infrastructure, and associated development, at the existing and planned expanded…
Maynooth 220kV Substation , Taghadoe , Co. Kildare
2460364KildareLodged 25 Apr 2024Infrastructure
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedEnergy
Development consisting of (a) A High Inertia Synchronous Compensator (HISC) compound containing 1 No. HISC…
Ballysumaghan , Sooey , County Sligo
22352SligoLodged 27 Oct 2022
- GrantedEnergy
Permission for a synchronous compensator (electricity grid stabilization) development within the townland of…
Killeena, Knockraha, Co.Cork,
224488corkLodged 7 Mar 2022
- GrantedEnergy
(A) A HIGH INTERTIA SYNCHRONOUS COMPENSATOR (HISC) COMPOUND CONTAINING 1 NO. HISC UNIT ENCLOSED WITHIN A…
KILPADDOGE , TARBERT , CO KERRY
21549KerryLodged 25 May 2021
- InvalidInfrastructure
Mayne Stability Limited intends to apply for permission for a period of 10 years for the development of…
The site of c. 0.94 ha at lands South of Belcamp 220 kV Substation, Belcamp, Dublin 17
4091/21Dublin CityLodged 15 Dec 2021
- RefusedEnergy
For a 10 year planning permission to develop a synchronous condenser grid support facility, which will…
Dunnstown , Brannockstown , Naas
211371KildareLodged 24 Sept 2021
- GrantedEnergy
THE DEVELOPMENT WILL CONSIST OF A GRID STABILISATION FACILITY COMPRISING OF: THE CONSTRUCTION UP TO 4 NO.…
KILPADDOGE , TARBERT , CO KERRY
19115KerryLodged 12 Feb 2019
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.