Baldonnell, Co. Dublin.
Road improvements and new access roads for a business park in Baldonnell, including the demolition of a house.
SD088/0010 · South Dublin County Council · Lodged 14 October 2008
- Reference
- SD088/0010
- Authority
- South Dublin County Council
- Register status
- In progress
- Type
- Application Under Part 8
- Received
- 14 October 2008
Summary
AI-generatedThe project involves widening 300 metres of Baldonnell Road with new cycletracks and footpaths, alongside constructing multiple roundabouts. It also includes building new dual and single carriageways to access the proposed Milltown Business and Technology Park, requiring the demolition of an existing house.
Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.
Official record
Development description
- Construct baldonnell road improvement scheme & access road to proposed milltown business and technology park, clondalkin, dublin 22 as described below: construction of 300 linear metres of new widened carriageway on baldonnell road complete with grass verge on either side of the road; construction of cycletracks and footpaths; construction of 1 no. Roundabout at the entrance to the proposed milltown business and technology park ; construction of 200 metres of dual carriageway within the proposed milltown business and technology park; construction of 150 metres of single carriageway within the proposed milltown business and technology park; construction of 2 no. Roundabouts within the proposed milltown business and technology park; upgrade of baldonnell road/aylmer road junction as a small roundabout; demolition of existing house and provision of ancillary service works. Plans and particulars of the proposed developments are available for inspection, or purchase at a fee not exceeding the reasonable cost of making a copy, at:- south dublin county council, county hall, tallaght, dublin 24, between the hours of 9.00 am
- 5.00 pm monday to thursday and 9.00 am
- 4.30 pm friday (inspection and purchase); south dublin county council, civic offices ,clondalkin, dublin 22, between the hours of 9.00 am
- 5.00 pm monday to thursday and 9.00 am
- 4.30 pm friday (inspection and purchase); clondalkin library, monastery road, clondalkin, dublin 22, between the hours of 9.45am 8.00pm monday to thursday and 9.45 4.30pm friday and saturday (inspection only) from monday 21st july to monday 1st september 2008. Submissions and observations with respect to this matter, dealing with the proper planning and sustainable development of the area, in which the development would be situated may be made in writing to: senior executive officer, roads department, south dublin county council, county hall, tallaght, dublin
- Closing date for receipt of submissions is up to and including 4.30 pm on friday 19th september 2008
Land-use zoning
What this land is zoned for
“To provide for enterprise and employment related uses”
National zoning type: Industrial, enterprise, employment
Objective set by the South Dublin County Development Plan 2022-2028 (2022–2028). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.
Read the zoning objectives in the development planBuilt & sold
What happened next
Beyond the decision: whether this development was built, and what property here has sold for.
Recent sales nearby
within 500 m| Address | Date | Price | Distance |
|---|---|---|---|
| Apartments 1-33, Block 8 Nangor Hall, Kilcarbery Grange | Dec 2025 | €12,943,276 | 459 m |
Nearby properties, not this site — a guide to local values.
Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.
Key dates
Timeline
- Application received14 October 2008
- Decision issued8 December 2008
In the area
Applications near this site
Other planning applications within about 500 m — what else is being proposed or built nearby.
- Granted60 m away
Single storey ESB substation (27sq.m) that will be accessed from the north off the Grange Castle South Access…
Grange Castle Business Park South, Townland of Milltown and bounding the Grange Castle South Access Road to the North, Baldonnel, Dublin 22
SD19A/0300South DublinLodged 24 Sept 2019Infrastructure
- Granted140 m away
Permission for a period of ten years for development at this site of 16.5 hectares that is located within…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0121South DublinLodged 16 Jul 2020Industrial
- Granted140 m away
Retention of single storey client control room (248.5sq.m) associated with the planned future substation that…
Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0244South DublinLodged 24 Sept 2020Retention
- Granted180 m away
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134/EP2South DublinLodged 15 Sept 2023Industrial
- Granted180 m away
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134South DublinLodged 30 Jul 2018Commercial
- Refused180 m away
Demolition of the existing single storey house of 'Erganagh' and the construction of a two storey data centre…
Grange Castle Business Park, Clondalkin, Dublin 22
SD18A/0134/EPSouth DublinLodged 14 Jul 2023Industrial
- Granted180 m away
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 —…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0295/EPSouth DublinLodged 2 Apr 2026Retention
- Granted180 m away
Amendments and modifications to the permitted data centre development granted under Reg. Ref. SD18A/0134 —…
Townlands within Grange Castle South Business Park, Baldonnel, Dublin 22
SD20A/0295South DublinLodged 17 Feb 2021Commercial
Related developments
Similar applications
Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.
- GrantedInfrastructure
Construct a new access road off the Nangor Road, Clondalkin Dublin 22 as described below:- — Construction of…
Nangor Road, Clondakin, Dublin 22
SD118/0001South DublinLodged 16 May 2011
- GrantedInfrastructure
The proposed Celbridge Link Road is a new two-way single carriageway road alignment linking the Adamstown SDZ…
Celbridge Link Road, Adamstown, Co. Dublin
SD178/0009South DublinLodged 21 Dec 2017
- GrantedInfrastructure
Tallaght to Ballyboden Cyce Route Scheme: proposed works will comprise the following — Construction of new…
Tallaght to Ballyboden Cyce Route Scheme
SD128/0003South DublinLodged 6 Sept 2012
- GrantedInfrastructure
(1) Provision of a direct road link between Belgard Square North and the Cookstown Road. (2) A new signalised…
Belgard Square North/Cookstown Industrial Estate, Tallaght, Dublin 24
SD178/0007South DublinLodged 13 Nov 2017
- GrantedCommercial
Construct the Clondalkin Round Tower Visitors Centre and Public Gardens. Development of the visitors’ centre…
Millview Terrace and Tower Road, Clondlakin, Dublin 22
SD148/0003South DublinLodged 20 May 2014
- GrantedInfrastructure
Proposed Traffic Calming Measures: The proposed works consist of the following: (1) the provision of standard…
Aylesbury/Cushlawn, Tallaght, Dublin 24
SD088/0007South DublinLodged 14 Oct 2008
Community
Discussion
What local people think about this application.
Community sentiment
No votes yetNobody has voted on this application yet.
Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.
Sign in to have your say on this application.
No comments yet. Be the first to say what you think about this application.
Sign in to join the discussion on this application.
Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.