Planning Permission Ireland
GrantedIndustrialDecided 2 June 2026

Gneevebane Oldtown Farthingstown Castlelost and Kiltotan and Collinstown, Rochfortbridge, County Westmeath

Development of a massive data centre facility and energy resource near Rochfortbridge.

2560344 · Westmeath County Council · Lodged 8 July 2025

Reference
2560344
Authority
Westmeath County Council
Register status
Appealed
Type
PERMISSION
Received
8 July 2025

Summary

AI-generated

The proposed development on a 243-hectare site includes six large data buildings, a security control building, and six fuel cell towers. It also features water treatment plants, gas installation compounds, and a 33kV IPP building.

Industrialdata centreenergyinfrastructuregas
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

  • The development of a data centre facility and decentralised energy resource within an overall development boundary area of 243 hectares comprising
  • 1 no. Security control building (floor area 23.5m2)
  • 6 no. New data buildings including administration blocks (each 228m x 62m x 18m high), 6 no. Mv switch room buildings, within a secure campus having an area of 39 hectares, 1 no. Fire water tank (volume: 2000m3), pump house and proprietary modular water treatment plant
  • 6 no. Fuel cell towers (each 89m x 29m x 20m high), 2 no. Chilled water tanks (volume: 1000m3 each), pump house, ancillary water tank (volume: 2000m3), carbon dioxide process building (30.7m x 15.7m x 11.3m high) and 16 no. Carbon dioxide storage tanks (100 tonnes each)
  • Ancillary equipment compound including a storage building (30.7m x 10.7m x 9.7m high), 2 no. Diesel generators, fire water tank (volume: 2000m3) and pump house and proprietary modular water treatment plant
  • Above ground gas installation (agi) compound including a boiler/instrument kiosk, regulator/metal skid kiosk and connection to the existing gas network within the site
  • 33kv ipp building (60.9m x 18.4m x 16.8m high), 1 no. Telecoms tower 36m high and compound
  • Fuel cell ipp building (40m x 9.8m x 7.1m high) and compound
  • Solar farm ipp building (30m x 9.8m x 7.1m high) and compound
  • Battery compound including 138 no. Battery enclosures & 138 no. Medium voltage power stations (mvps), ipp building (40m x 9.8m x 7.1m high) and fire water tank (volume: 500m3)
  • Proprietary modular water treatment plant serving the solar farm ipp building and battery compound ipp building
  • Solar farm (168 hectares) to the east of the data campus facility including solar arrays measuring (10.2m x 6.9m), (20.4m x 6.9m) & (30.6 x 6.9m), 45 no. Medium voltage power stations (mvps), 5 no. Weather stations, river crossings, internal gravel access roads, security fencing and gates, 3 no. Temporary construction compounds, cable crossings in the r446, l11272 & l51251 public roads, and cable crossing under the m6 using horizontal directional drilling
  • Connection to public sewer under the r446 public road
  • New emergency only access/egress from the r446 public road
  • Access/egress to the data centre campus facility through the existing castlelost flexgen and gis substation access to the r446
  • Demolition of the existing derelict dwelling and agricultural sheds
  • All associated site works including

Key dates

Timeline

  1. Application received8 July 2025
  2. Further information requested1 September 2025
  3. Further information received11 February 2026
  4. Decision due2 June 2026
  5. Decision issued2 June 2026
  6. Appeal submitted23 June 2026

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.