Planning Permission Ireland
GrantedInfrastructureDecided 12 July 2018

Galway 110kV Electrical Substation, Ballybane Industrial Estate, Bothar na Mine (Townland of Ballybaan Beg)

Construction of a new 15-meter-high gas insulated switchgear building and associated works at the Galway 110kV substation.

1810 · Galway City Council · Lodged 12 January 2018

Reference
1810
Authority
Galway City Council
Register status
Decided
Type
PERMISSION
Received
12 January 2018
Residential units
1
Floor area
100 m²

Summary

AI-generated

The development consists of a new twelve-bay 110kV Gas Insulated Switchgear (GIS) building measuring approximately 700 sq.m. within the existing substation. It includes replacing three overhead line towers with line cable interface masts, installing underground cables, and creating temporary and permanent access modifications.

Infrastructuresubstationinfrastructureelectricity
Storey
1

Generated from the description above by an AI model and may contain mistakes. The council’s description is the authoritative record.

Official record

Development description

Permission for development which will consist of: the construction of a new twelve bay 110kv gas insulated switchgear (gis) building located entirely within the southern portion of the existing galway 110kv substation. The proposed gis building will measure approximately 700 sq. M. With a height of approximately 15 meters; associated development includes: the replacement of three existing 110kv overhead line towers within the substation with three line cable interface masts (lcim) proximate to the existing towers to facilitate access of existing transmission circuits to the proposed gis building by means of underground cables; provision of a temporary internal access route, and vehicular access gate at the south-eastern boundary of the existing substation site to facilitate construction activities. This internal access route and gate will be removed and the substation boundary reinstated upon completion of the development; improvements to the existing vehicular access arrangements on the south-western boundary of the existing substation, in particular reducing the total number of existing vehicular entrances from two to one at this location; associated boundary treatment to the existing south-eastern, southern and south-western substation boundaries, in particular the construction of a new 3m high wall along these boundaries; all associated and ancillary development and site works including provision and/or replacement of electrical equipment, drainage works, laying of new or replacement cables and the diversion of existing cables

Land-use zoning

What this land is zoned for

Enterprise Industry and Related UsesSI
To provide for Enterprise, Industral and Related uses

National zoning type: General industry

Objective set by the Galway City Development Plan 2023 - 2029 (2023–2029). The planning authority decides each application on its own merits — this is the zoning context, not a compliance assessment.

Read the zoning objectives in the development plan

Built & sold

What happened next

Beyond the decision: whether this development was built, and what property here has sold for.

Recent sales nearby

within 500 m
Residential Property Price Register sales within 500 metres of this site
AddressDatePriceDistance
115 Monivea Park, Ballybane, GalwayMar 2026€351,000194 m
101 Monivea Park, Ballybane, GalwayMay 2026€375,000197 m
6 Gort Leinn, Old Monilea Rd, GalwayDec 2025€295,000317 m
Apt 10, Dun Breathnach, Old Ballybane RdSept 2025€155,000339 m
67 Monivea Park, Ballybane, GalwaySept 2025€325,000342 m
11 Dun Leinn, Old Monivea Rd, GalwayFeb 2026€280,000343 m
33 Bothar Na Mine, Kinvaraprice excludes VATSept 2025€396,500358 m
6 Monivea Park, Ballybane, GalwayDec 2025€342,000417 m

Nearby properties, not this site — a guide to local values.

Sources: Building Control Management System (commencement notices) and the Residential Property Price Register, licensed under CC BY 4.0. Records are matched to this application by location and may not be exhaustive; always confirm against the official source before relying on them.

Key dates

Timeline

  1. Application received12 January 2018
  2. Further information requested7 March 2018
  3. Further information received15 June 2018
  4. Decision due12 July 2018
  5. Decision issued12 July 2018
  6. Grant issued15 August 2018
  7. Permission expiry14 August 2023

In the area

Applications near this site

Other planning applications within about 500 m — what else is being proposed or built nearby.

Related developments

Similar applications

Ranked by what these developments actually propose, not by matching words — so you can see how comparable applications were decided.

Community

Discussion

What local people think about this application.

Nobody watching yet

Community sentiment

No votes yet

Nobody has voted on this application yet.

Community sentiment — a straw poll of people who visited this page, not a statutory submission. To make a valid observation you must submit it to the planning authority.

Sign in to have your say on this application.

No comments yet. Be the first to say what you think about this application.

Sign in to join the discussion on this application.

Comments are moderated and are the opinions of the people who wrote them. They form no part of the statutory planning process — to make a valid observation you must submit it to the planning authority.