Multi-Generational Self-Build in Ireland — A 245 m² Galway Build, the Numbers and the Gotchas

Last updated 30/6/2026 · Reviewed 30/6/2026
On this page

Multi-generational in Co. Galway: 245 m², finished 2023, main contractor. Build cost: €640,000 (€2,610/m²). Two self-contained units under one roof: main 4-bed (165 m²) + granny flat 1-bed (80 m²). Shared utility, separate entrances, separate metering. Build: timber frame, slate roof, MVHR in both units, 9 kW air-to-water heat pump, 6 kWp solar PV. Gotchas: the granny flat needed separate metering (BER A1 for the main house + BER A3 for the granny flat), planning for the dual use (the planner wanted the granny flat to be removable, not a permanent separate dwelling), soundproofing between the units (the wall between is double-stud with acoustic insulation). Outcome: finished in 14 months. The granny flat is currently used by the owner's mother; will become a teenager's retreat in 5 years. The owners credit the success to: a clear brief that named the multi-generational use, an architect with two recent multi-gen builds, and a quantity surveyor who caught the metering issue early.

TL;DR

  • Multi-generational (Co. Galway, 245 m², 2023): €640,000 build, main contractor. Build cost €2,610/m².

  • Two self-contained units under one roof: main 4-bed + granny flat 1-bed. Shared utility, separate entrances.

  • Gotchas: the granny flat needed separate metering (BER A1 + BER A3 for the two units), planning for the dual use, soundproofing between the units.

When this matters most

You're researching case studies for a multi-generational build.

When this doesn't apply

You've already started your build.

Frequently asked questions

How much did a 245 m² multi-gen build cost in Galway in 2023?

€640,000 build, main contractor. Build cost €2,610/m². Two units: main 4-bed (165 m²) + granny flat 1-bed (80 m²). Total project cost €850,000–€900,000.

What were the gotchas on this build?

The granny flat needed separate metering (BER A1 + BER A3 for the two units), planning for the dual use (removable, not a permanent separate dwelling), soundproofing between the units.

How long did the build take?

14 months on site. The dual-unit design and the metering added 2 months. The granny flat is currently used by the owner's mother; will become a teenager's retreat in 5 years.

Sources

SCSI, Construction Cost Database 2024. https://www.scsi.ie/

Frequently asked questions

How much did a 245 m² multi-gen build cost in Galway in 2023?

€640,000 build, main contractor. Build cost €2,610/m². Two units: main 4-bed (165 m²) + granny flat 1-bed (80 m²). Total project cost €850,000–€900,000.

What were the gotchas on this build?

The granny flat needed separate metering (BER A1 + BER A3 for the two units), planning for the dual use (removable, not a permanent separate dwelling), soundproofing between the units.

How long did the build take?

14 months on site. The dual-unit design and the metering added 2 months. The granny flat is currently used by the owner's mother; will become a teenager's retreat in 5 years.