Land and Site Assessment — What Decides a Site Is Buildable in Ireland

Last updated 30/6/2026 · Reviewed 30/6/2026
On this page

Five things decide this: planning status, access, soil, water, wastewater. Any one can kill a sale-agreed purchase.

[@portabletext/react] Unknown block type "span", specify a component for it in the `components.types` prop

When this matters most

You're still choosing sites, you've gone sale-agreed, or you've just inherited land and don't know if it's buildable.

When this doesn't apply

You already own a buildable site with full planning permission, tests done, and an engineer appointed.

Decision matrix

If: Site is outside the rural settlement boundary and never had planning

Then: Check the county development plan local-needs policy first. Rural housing policy tightened in most counties since 2022.

If: Site has planning permission but it's over 5 years old

Then: It may have lapsed. Check expiry date; renewal is rarely automatic.

If: Site has no public sewer within reasonable distance

Then: You need a Domestic Wastewater Treatment System (DWWTS) with percolation area. Get a percolation test before exchange of contracts.

If: Ground is rock, gravel, or sand (Class 1–2)

Then: Standard strip foundation likely. Cheapest foundation.

If: Ground is clay, silt, made ground (Class 3–4)

Then: Raft foundation likely. Add €15,000–€25,000 to budget.

If: Ground is peat, soft clay, or fill (Class 5+)

Then: Piled raft or driven piles. Add €40,000–€80,000.

Frequently asked questions

How much does a site assessment cost in Ireland?

€1,500–€4,000 for a soil test, percolation test, and water yield test together. Engineers typically charge €300–€600 for a desktop feasibility study on top.

What is a percolation test?

Measures how fast water drains into your soil. EPA Code of Practice sets minimum standards (e.g. T≤90 minutes for soil, ≤30 for subsoil); results dictate which wastewater system your site can take.

Can I build on a site with no planning permission?

Not in nearly any case for a one-off house. Some very limited agricultural and maintenance works are exempt under Schedule 2 of the Planning Regulations. Building a new dwelling is not exempt.

What is ribbon development?

A planning policy: building houses strung along a single rural road. Most county development plans refuse ribbon development outright. If your site is in a ribbon position, planning is very likely to be refused.

How deep does a borehole need to be for a private well?

Site-specific. Typical Irish domestic wells: 30–80 m deep. Yield (litres per minute) is what matters, not depth. Get an EIS test before purchase.

Is radon a problem on rural Irish sites?

Yes, particularly in the southeast (Co. Carlow, Wexford, parts of Wicklow). 1 in 10 Irish homes has elevated radon. Your engineer will specify a radon barrier and possibly a sump.

Sources

EPA, Code of Practice: Domestic Wastewater Treatment Systems (2018, updated 2021). https://www.epa.ie/publications/compliance--enforcement/waste-water/

Geological Survey Ireland, Irish Soil Classification System. https://www.gsi.ie/

Department of Housing, Rural Housing: Sustainable Rural Communities Guidelines for Planning Authorities 2020. https://www.gov.ie/

Quick decision matrix

If your situation isThen choose
Site is outside the rural settlement boundary and never had planningCheck the county development plan local-needs policy first. Rural housing policy tightened in most counties since 2022.
Site has planning permission but it's over 5 years oldIt may have lapsed. Check expiry date; renewal is rarely automatic.
Site has no public sewer within reasonable distanceYou need a Domestic Wastewater Treatment System (DWWTS) with percolation area. Get a percolation test before exchange of contracts.
Ground is rock, gravel, or sand (Class 1–2)Standard strip foundation likely. Cheapest foundation.
Ground is clay, silt, made ground (Class 3–4)Raft foundation likely. Add €15,000–€25,000 to budget.
Ground is peat, soft clay, or fill (Class 5+)Piled raft or driven piles. Add €40,000–€80,000.

Frequently asked questions

How much does a site assessment cost in Ireland?

€1,500–€4,000 for a soil test, percolation test, and water yield test together. Engineers typically charge €300–€600 for a desktop feasibility study on top.

What is a percolation test?

Measures how fast water drains into your soil. EPA Code of Practice sets minimum standards (e.g. T≤90 minutes for soil, ≤30 for subsoil); results dictate which wastewater system your site can take.

Can I build on a site with no planning permission?

Not in nearly any case for a one-off house. Some very limited agricultural and maintenance works are exempt under Schedule 2 of the Planning Regulations. Building a new dwelling is not exempt.

What is ribbon development?

A planning policy: building houses strung along a single rural road. Most county development plans refuse ribbon development outright. If your site is in a ribbon position, planning is very likely to be refused.

How deep does a borehole need to be for a private well?

Site-specific. Typical Irish domestic wells: 30–80 m deep. Yield (litres per minute) is what matters, not depth. Get an EIS test before purchase.

Is radon a problem on rural Irish sites?

Yes, particularly in the southeast (Co. Carlow, Wexford, parts of Wicklow). 1 in 10 Irish homes has elevated radon. Your engineer will specify a radon barrier and possibly a sump.

When this matters most

You're still choosing sites, you've gone sale-agreed, or you've just inherited land and don't know if it's buildable.

When this doesn't apply

You already own a buildable site with full planning permission, tests done, and an engineer appointed.

Briefs in this stage

17 in-depth answers for this stage of the build. Pick the one that matches your question.

Where to go next

Free pre-planning reportCheck a site before you apply
Map of applicationsEvery application on one map, with zoning and heritage layers
AreasCounties and towns
Planning statisticsThe national picture, and every council side by side
CommencementsWhat actually got built
Property salesWhat it sold for
Ask the planning assistantPlain-English questions