A-Rated ICF Self-Build in Ireland — A 210 m² Wicklow Build, the Numbers and the Gotchas

Last updated 30/6/2026 · Reviewed 30/6/2026
On this page

A-rated ICF on a slope (Co. Wicklow, 210 m², 2024): €610,000 build, main contractor. Site works doubled the original 10% allowance.

A-rated ICF on a slope in Co. Wicklow: 210 m², finished 2024, main contractor. Build cost: €610,000 (€2,900/m²). Site: 1.5 acres, sloped (3 m across the footprint), rural housing local needs. Build: ICF walls, slate roof, MVHR, 9 kW air-to-water heat pump, 6 kWp solar PV, BER A1. Gotchas: site-specific cost (slope, long connection runs, treatment system, retaining walls) doubled the original 10% allowance — €80,000 on site works alone. The owners underestimated the cost of the slope. The engineer specified stepped foundations and a retaining wall that added €25,000 to the foundation cost. Outcome: finished in 14 months. BER A1 confirmed. The owners credit the success to: a quantity surveyor who caught the slope cost early, a main contractor with two recent ICF builds, and a 15% contingency (which absorbed the slope overrun).

When this matters most

You're researching case studies for a sloped ICF build.

When this doesn't apply

You've already started your build.

Sources

SCSI, Construction Cost Database 2024. https://www.scsi.ie/

Frequently asked questions

How much did a 210 m² ICF build cost in Wicklow in 2024?

€610,000 build, main contractor. Build cost €2,900/m². Plus site works (€80,000), fees, and VAT: total project cost €800,000–€850,000. BER A1.

What were the gotchas on this build?

Site-specific cost (slope, long connection runs) doubled the original 10% allowance. €80,000 on site works. The engineer specified stepped foundations and a retaining wall that added €25,000 to the foundation cost.

How long did the build take?

14 months on site. The slope added 2 months to the foundation phase. ICF walls were fast once the foundation was done.

When this matters most

You're researching case studies for a sloped ICF build.

When this doesn't apply

You've already started your build.

Where to go next

Free pre-planning reportCheck a site before you apply
Map of applicationsEvery application on one map, with zoning and heritage layers
AreasCounties and towns
Planning statisticsThe national picture, and every council side by side
CommencementsWhat actually got built
Property salesWhat it sold for
Ask the planning assistantPlain-English questions